Notes to SEFA
Title: Note 1 - Purpose of the Schedule
Accounting Policies: Basis of Accounting
Expenditures reported on the Schedule are reported using the same accounting policies and basis of accounting as the financial statements. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement.
De Minimis Rate Used: Y
Rate Explanation: FTR has elected to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance.
The accompanying schedule of expenditures of federal awards (the Schedule) includes the
federal award activity of the Friends of the Teton River, Inc. (FTR) for the year ended June 30,
2024. The information in this Schedule is presented in accordance with the requirements of Title
2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost
Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the
Schedule presents only a selected portion of the operations of FTR, it is not intended to and does
not present the financial position, changes in net assets, or cash flows of FTR.
Title: Note 2 - Summary of Significant Accounting Policies
Accounting Policies: Basis of Accounting
Expenditures reported on the Schedule are reported using the same accounting policies and basis of accounting as the financial statements. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement.
De Minimis Rate Used: Y
Rate Explanation: FTR has elected to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance.
Basis of Accounting
Expenditures reported on the Schedule are reported using the same accounting policies and basis
of accounting as the financial statements. Such expenditures are recognized following the cost
principles contained in the Uniform Guidance, wherein certain types of expenditures are not
allowable or are limited as to reimbursement.
Assistance Listing Numbers
Uniform Guidance requires that the Schedule show the total expenditures for each of FTR’s
federal financial assistance programs as identified in the Assistance Listing Number (ALN). The
ALN is a government-wide compendium of individual federal programs. Each program included
in the ALN is assigned a five-digit program identification number (ALN number).
Major Programs
Uniform Guidance establishes the levels of expenditures or expenses and other criteria to be used
in defining major programs. Major programs have been noted on the Schedule of Findings and
Questioned Costs in accordance with those definitions.
Indirect Costs
The Schedule includes programs operated by FTR which include a portion of costs associated
with general activities that are allocated to federal financial assistance programs using direct
labor as a basis of allocation.
FTR has elected to use the 10% de minimis indirect cost rate allowed under the Uniform
Guidance.