Findings

ID Ref Severity Repeat Requirement
522409 2024-001 Significant Deficiency - L
522410 2024-001 Significant Deficiency - L
1098851 2024-001 Significant Deficiency - L
1098852 2024-001 Significant Deficiency - L

Contacts

Name Title Type
ZXRMKZBNC8Y1 Laura C. Leach Auditee
7038420740 Dawit Negari Auditor
No contacts on file

Notes to SEFA

Title: A. Basis of Presentation Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following cost principles contained in Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: The Commission has not elected to use the 10 percent de minimis indirect cost rate allowed under Uniform Guidance. The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal grant activity of the Commission under programs of the federal government for the year ended June 30, 2024. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the Commission, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Commission.
Title: C. Federal Audits Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following cost principles contained in Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance), wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: The Commission has not elected to use the 10 percent de minimis indirect cost rate allowed under Uniform Guidance. The allowability of certain costs under government grants is subject to audit by the contracting agency. Certain indirect costs charged to grants are subject to revisions based on government audits of those costs. Management believes that grant costs are consistent with applicable government cost principles, and costs subsequently disallowed, if any, upon audit by the government would not be material.

Finding Details

Criteria: According to grant terms & conditions and 2 CFR Section 200.332, all awardees of applicable grants and cooperative agreements are required to report to the Federal Funding Accountability and Transparency Act (FFATA) Subaward Reporting System (FSRS) on all subawards over $30,000. Condition: The Commission did not provide timely FFATA reporting for ALN #11.469 and #11.472 subawards subject to the FFATA reporting requirements. Context: This is a condition identified based on review of grant terms and conditions and 2 CFR Section 200.332. Cause: The Commission was not aware of this reporting requirement. Effect: The Commission is not in compliance with FFATA reporting requirements for fiscal year 2024. Identification of a Repeat Finding: This is not a repeat finding. Recommendation: We suggest that management review all awards for subrecipients and ensure that FFATA reporting is completed in a timely manner for subawards subject to the requirements. Views of Responsible Officials: The Commission agrees with the finding. Planned Corrective Action: The Commission will review all subawards for subrecipients and ensure that FFATA reporting is completed in a timely manner for subawards subject to the requirements. The Commission will add a clause in our Sub-awards stating this requirement. Responsible Official: Laura Leach, Director of Finance and Administration Anticipated Completion Date: December 31, 2024
Criteria: According to grant terms & conditions and 2 CFR Section 200.332, all awardees of applicable grants and cooperative agreements are required to report to the Federal Funding Accountability and Transparency Act (FFATA) Subaward Reporting System (FSRS) on all subawards over $30,000. Condition: The Commission did not provide timely FFATA reporting for ALN #11.469 and #11.472 subawards subject to the FFATA reporting requirements. Context: This is a condition identified based on review of grant terms and conditions and 2 CFR Section 200.332. Cause: The Commission was not aware of this reporting requirement. Effect: The Commission is not in compliance with FFATA reporting requirements for fiscal year 2024. Identification of a Repeat Finding: This is not a repeat finding. Recommendation: We suggest that management review all awards for subrecipients and ensure that FFATA reporting is completed in a timely manner for subawards subject to the requirements. Views of Responsible Officials: The Commission agrees with the finding. Planned Corrective Action: The Commission will review all subawards for subrecipients and ensure that FFATA reporting is completed in a timely manner for subawards subject to the requirements. The Commission will add a clause in our Sub-awards stating this requirement. Responsible Official: Laura Leach, Director of Finance and Administration Anticipated Completion Date: December 31, 2024
Criteria: According to grant terms & conditions and 2 CFR Section 200.332, all awardees of applicable grants and cooperative agreements are required to report to the Federal Funding Accountability and Transparency Act (FFATA) Subaward Reporting System (FSRS) on all subawards over $30,000. Condition: The Commission did not provide timely FFATA reporting for ALN #11.469 and #11.472 subawards subject to the FFATA reporting requirements. Context: This is a condition identified based on review of grant terms and conditions and 2 CFR Section 200.332. Cause: The Commission was not aware of this reporting requirement. Effect: The Commission is not in compliance with FFATA reporting requirements for fiscal year 2024. Identification of a Repeat Finding: This is not a repeat finding. Recommendation: We suggest that management review all awards for subrecipients and ensure that FFATA reporting is completed in a timely manner for subawards subject to the requirements. Views of Responsible Officials: The Commission agrees with the finding. Planned Corrective Action: The Commission will review all subawards for subrecipients and ensure that FFATA reporting is completed in a timely manner for subawards subject to the requirements. The Commission will add a clause in our Sub-awards stating this requirement. Responsible Official: Laura Leach, Director of Finance and Administration Anticipated Completion Date: December 31, 2024
Criteria: According to grant terms & conditions and 2 CFR Section 200.332, all awardees of applicable grants and cooperative agreements are required to report to the Federal Funding Accountability and Transparency Act (FFATA) Subaward Reporting System (FSRS) on all subawards over $30,000. Condition: The Commission did not provide timely FFATA reporting for ALN #11.469 and #11.472 subawards subject to the FFATA reporting requirements. Context: This is a condition identified based on review of grant terms and conditions and 2 CFR Section 200.332. Cause: The Commission was not aware of this reporting requirement. Effect: The Commission is not in compliance with FFATA reporting requirements for fiscal year 2024. Identification of a Repeat Finding: This is not a repeat finding. Recommendation: We suggest that management review all awards for subrecipients and ensure that FFATA reporting is completed in a timely manner for subawards subject to the requirements. Views of Responsible Officials: The Commission agrees with the finding. Planned Corrective Action: The Commission will review all subawards for subrecipients and ensure that FFATA reporting is completed in a timely manner for subawards subject to the requirements. The Commission will add a clause in our Sub-awards stating this requirement. Responsible Official: Laura Leach, Director of Finance and Administration Anticipated Completion Date: December 31, 2024