Audit 340525

FY End
2024-06-30
Total Expended
$920,061
Findings
0
Programs
5

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
17.274 Project Youthbuild - Youthbuild 23-26 $592,298 Yes 0
21.027 Coronavirus State and Local Fiscal Recovery Funds $153,532 - 0
94.006 Americorps State and National - 23-24 $81,412 - 0
17.274 Project Youthbuild - Youthbuild 21-24 $70,885 Yes 0
94.006 Americorps State and National - 22-23 $21,934 - 0

Contacts

Name Title Type
MJ6KJYM4XCF9 Jonathan Leslie Auditee
3522253307 Ed Moss Auditor
No contacts on file

Notes to SEFA

Title: NOTE 1 - BASIS OF PRESENTATION Accounting Policies: The accompanying schedule of expenditures of federal awards is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the basic financial statements. De Minimis Rate Used: N Rate Explanation: The Organization has elected to not use the 10% de minimis indirect cost rate for its federal programs for the year ended June 30, 2024. The indirect cost rates used on the Organization's federal program are determined by the relevant federal agency. The accompanying schedule of expenditures of federal awards is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the basic financial statements.
Title: NOTE 2 -CONTINGENCY Accounting Policies: The accompanying schedule of expenditures of federal awards is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the basic financial statements. De Minimis Rate Used: N Rate Explanation: The Organization has elected to not use the 10% de minimis indirect cost rate for its federal programs for the year ended June 30, 2024. The indirect cost rates used on the Organization's federal program are determined by the relevant federal agency. Amounts received or receivable from grantor agencies are subject to audit and adjustment by those agencies. Any disallowed claims, including amounts already received, might constitute a liability for the return of those funds. In the opinion of management, all grant expenditures were in compliance with the terms of the grant agreements and applicable federal laws and regulations.
Title: NOTE 3 - INDIRECT COST RATES Accounting Policies: The accompanying schedule of expenditures of federal awards is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the basic financial statements. De Minimis Rate Used: N Rate Explanation: The Organization has elected to not use the 10% de minimis indirect cost rate for its federal programs for the year ended June 30, 2024. The indirect cost rates used on the Organization's federal program are determined by the relevant federal agency. The Organization has elected to not use the 10% de minimis indirect cost rate for its federal programs for the year ended June 30, 2024. The indirect cost rates used on the Organization's federal program are determined by the relevant federal agency.