Audit 333123

FY End
2024-09-30
Total Expended
$2.33M
Findings
0
Programs
2
Organization: Northcliff Gardens Inc. (OK)
Year: 2024 Accepted: 2024-12-17

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
14.157 Supportive Housing for the Elderly $2.30M Yes 0
14.182 Section 8 New Construction and Substantial Rehabilitation $29,643 - 0

Contacts

Name Title Type
Q5Y4B2J45QL5 Karen Canavan Auditee
4053290933 Shoaib Khar Auditor
No contacts on file

Notes to SEFA

Accounting Policies: NOTE 1 – BASIS OF PRESENTATION The accompanying Schedule of Expenditures of Federal Awards (Schedule) includes the federal grant activity of the Northcliff Gardens Inc., Oklahoma (Corporation) under programs of the federal government for the year ended September 30, 2024. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements of Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the Corporation, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Corporation. NOTE 2 – SUMMARY OF SIGNIFICANT ACCOUNTING POLICIES Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. NOTE 3 – SOURCES OF FUNDING The schedule includes all grants and contracts entered into directly between the Authority and agencies and departments of the federal government, as well as federal funds passed through to the Authority by primary recipients. The Authority provided no part of its direct grant federal dollars to sub-recipients. NOTE 4 – SUB-RECIPIENTS There were no sub-recipients for the year ended September 30, 2024. De Minimis Rate Used: N Rate Explanation: The Corporation has elected not to use the 10-percent de minimis indirect cost rate as allowed under the Uniform Guidance.