Audit 325841

FY End
2024-06-30
Total Expended
$899,417
Findings
0
Programs
2
Year: 2024 Accepted: 2024-10-24

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
14.181 Supportive Housing for Persons with Disabilities (section 811) $891,100 Yes 0
14.195 Section 8 Housing Assistance Payments Program $8,317 - 0

Contacts

Name Title Type
C1HFA87QQSV6 Patricia Walker Auditee
5019820528 Kyle Elmore Auditor
No contacts on file

Notes to SEFA

Title: Federal Loan Programs Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following, as applicable, either the cost principles contained in OMB A-122 or the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: The Project has elected not to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance. The Project did not have a balance outstanding due to any federal loan programs included in the Poject's basic financial statements at June 30, 2024. The Project's mortgage note with HUD through the Supportive Housing for Persons with Disabilities program was recorded as a contribution from HUD due to the terms described in the notes to the financial statements.
Title: Basis of Presentation Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following, as applicable, either the cost principles contained in OMB A-122 or the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: The Project has elected not to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance. The accompanying schedule of expenditures of federal awards (Schedule) includes the federal award activity of the Project under programs under the federal government for the year ended June 30, 2024. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the Project, it is not intended and does not present the financial position, changes in net assets, or cash flows of the Project.