Audit 324642

FY End
2024-06-30
Total Expended
$796,220
Findings
0
Programs
1
Organization: G.i.s Housing, Inc. (FL)
Year: 2024 Accepted: 2024-10-14
Auditor: Bdo USA PC

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
14.195 Project-Based Rental Assistance (pbra) $796,220 Yes 0

Contacts

Name Title Type
DNUTJ8K9VVK7 Tracey Boucher Auditee
7275231512 Gary Romer Auditor
No contacts on file

Notes to SEFA

Title: Basis of Presentation Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activities of G.I.S. Housing, Inc. (the Project), HUD Project No. 067-EH012-L8-WHC FL 29- 0706-201. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the schedule presents only a selected portion of the operations of the Project, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Project. Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in Uniform Guidance, wherein certain types of expenditures are not allowable or limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: The auditee did not use the de minimis cost rate. The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activities of G.I.S. Housing, Inc. (the Project), HUD Project No. 067-EH012-L8-WHC FL 29- 0706-201. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the schedule presents only a selected portion of the operations of the Project, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Project.
Title: Summary of Significant Accounting Policies Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activities of G.I.S. Housing, Inc. (the Project), HUD Project No. 067-EH012-L8-WHC FL 29- 0706-201. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the schedule presents only a selected portion of the operations of the Project, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Project. Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in Uniform Guidance, wherein certain types of expenditures are not allowable or limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: The auditee did not use the de minimis cost rate. Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in Uniform Guidance, wherein certain types of expenditures are not allowable or limited as to reimbursement.
Title: Indirect Costs Accounting Policies: The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activities of G.I.S. Housing, Inc. (the Project), HUD Project No. 067-EH012-L8-WHC FL 29- 0706-201. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the schedule presents only a selected portion of the operations of the Project, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Project. Expenditures reported on the Schedule are reported on the accrual basis of accounting. Such expenditures are recognized following the cost principles contained in Uniform Guidance, wherein certain types of expenditures are not allowable or limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: The auditee did not use the de minimis cost rate. The Project did not elect to use the 10% de minimis indirect cost rate allowed by the Uniform Guidance.