Audit 321681

FY End
2023-12-31
Total Expended
$2.63M
Findings
2
Programs
13
Organization: Wayne County (IN)
Year: 2023 Accepted: 2024-09-27

Organization Exclusion Status:

Checking exclusion status...

Contacts

Name Title Type
PVN5K6JQMSA6 Mark Hoelscher Auditee
7659739317 Beth Kelley, Cpa, Cfe Auditor
No contacts on file

Notes to SEFA

Accounting Policies: Note 1. Summary of Significant Accounting Policies A. Basis of Presentation The accompanying Schedule of Expenditures of Federal Awards (SEFA) includes the federal grant activity of the County under programs of the federal government for the year ended December 31, 2023. The information in the SEFA is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the SEFA presents only a select portion of the operations of the County, it is not intended to and does not present the financial position of the County. B. Other Significant Accounting Policies Expenditures reported on the SEFA are reported on the cash basis of accounting. Such expenditures are recognized following, as applicable, either the cost principles in OMB Circular A-87, Cost Principles for State, Local, and Indian Tribal Governments, or the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowed or are limited as to reimbursement. When federal grants are received on a reimbursement basis, the federal awards are considered expended when the reimbursement is received. De Minimis Rate Used: N Rate Explanation: Note 2. Indirect Cost Rate The County has elected not to use the 10 percent de minimis indirect cost rate allowed under the Uniform Guidance.

Finding Details

FINDING 2023-002 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): FY2021 Compliance Requirement: Reporting Audit Finding: Material Weakness Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2022-004. Condition and Context Recipients are required to submit quarterly or annually Project and Expenditure (P&E) reports to the U.S. Department of the Treasury (Treasury). The reporting periods, as well as the respective due dates, are based upon type of recipient and its population, as well as the recipient's allocation amount. Information to be reported includes projects funded, expenditures, and contracts for the appropriate reporting period. INDIANA STATE BOARD OF ACCOUNTS 16 WAYNE COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) The County was classified as a metropolitan county with a population below 250,000 residents that received an allocation of more than $10 million in Coronavirus State and Local Fiscal Recovery Funds (SLFRF). Therefore, quarterly P&E reports were due by January 31, 2022, and the last day of the month after the end of each quarter thereafter. The County filed the applicable quarterly P&E reports as required; however, the ARP Grant Manager prepared and submitted the reports without an oversight or review process in place to prevent, or detect and correct, errors. The lack of internal controls was a systemic issue throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." Cause A proper system of internal controls was not designed by management of the County, which would include segregation of key functions. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. There was no indication of an internal control process over reporting in place per inquiry with the officials and review of the reports. Effect Without the proper design or implementation of the components of a system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County design and implement a proper system of internal controls, including policies and procedures that would provide segregation of duties to ensure that appropriate reviews, approvals, and oversight are taking place so that the County continues to provide the Treasury with complete and accurate information in the P&E report. INDIANA STATE BOARD OF ACCOUNTS 17 WAYNE COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-002 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): FY2021 Compliance Requirement: Reporting Audit Finding: Material Weakness Repeat Finding This is a repeat finding from the immediately prior audit report. The prior audit finding number was 2022-004. Condition and Context Recipients are required to submit quarterly or annually Project and Expenditure (P&E) reports to the U.S. Department of the Treasury (Treasury). The reporting periods, as well as the respective due dates, are based upon type of recipient and its population, as well as the recipient's allocation amount. Information to be reported includes projects funded, expenditures, and contracts for the appropriate reporting period. INDIANA STATE BOARD OF ACCOUNTS 16 WAYNE COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) The County was classified as a metropolitan county with a population below 250,000 residents that received an allocation of more than $10 million in Coronavirus State and Local Fiscal Recovery Funds (SLFRF). Therefore, quarterly P&E reports were due by January 31, 2022, and the last day of the month after the end of each quarter thereafter. The County filed the applicable quarterly P&E reports as required; however, the ARP Grant Manager prepared and submitted the reports without an oversight or review process in place to prevent, or detect and correct, errors. The lack of internal controls was a systemic issue throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." Cause A proper system of internal controls was not designed by management of the County, which would include segregation of key functions. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. There was no indication of an internal control process over reporting in place per inquiry with the officials and review of the reports. Effect Without the proper design or implementation of the components of a system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County design and implement a proper system of internal controls, including policies and procedures that would provide segregation of duties to ensure that appropriate reviews, approvals, and oversight are taking place so that the County continues to provide the Treasury with complete and accurate information in the P&E report. INDIANA STATE BOARD OF ACCOUNTS 17 WAYNE COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.