Audit 319325

FY End
2023-12-31
Total Expended
$4.88M
Findings
2
Programs
13
Organization: Kosciusko County (IN)
Year: 2023 Accepted: 2024-09-11

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
496413 2023-001 Material Weakness - L
1072855 2023-001 Material Weakness - L

Contacts

Name Title Type
YZXAAA8REA77 Alyssa Schmucker Auditee
5743722325 Beth Kelley, Cpd, Cfe Auditor
No contacts on file

Notes to SEFA

Accounting Policies: Note 1. Summary of Significant Accounting Policies A. Basis of Presentation The accompanying Schedule of Expenditures of Federal Awards (SEFA) includes the federal grant activity of the County under programs of the federal government for the year ended December 31, 2023. The information in the SEFA is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the SEFA presents only a select portion of the operations of the County, it is not intended to and does not present the financial position of the County. B. Other Significant Accounting Policies Expenditures reported on the SEFA are reported on the cash basis of accounting. Such expenditures are recognized following, as applicable, either the cost principles in OMB Circular A-87, Cost Principles for State, Local, and Indian Tribal Governments, or the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowed or are limited as to reimbursement. When federal grants are received on a reimbursement basis, the federal awards are considered expended when the reimbursement is received. De Minimis Rate Used: N Rate Explanation: Note 2. Indirect Cost Rate The County has elected not to use the 10 percent de minimis indirect cost rate allowed under the Uniform Guidance.

Finding Details

FINDING 2023-001 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): ILBC-2023-Body Camera-00052 Pass-Through Entity: Indiana Department of Homeland Security Compliance Requirement: Reporting Audit Findings: Material Weakness, Other Matters INDIANA STATE BOARD OF ACCOUNTS 13 KOSCIUSKO COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Condition and Context The County Sheriff applied for the Indiana Local Body Camera Grant (ILBC). The grant is a reimbursable grant through the Indiana Department of Homeland Security. The County Sheriff was awarded this grant on January 1, 2023, with a grant cost amount of up to $31,920 to be spent from January 1, 2023 to December 31, 2023. The County Sheriff ordered body-worn cameras and other equipment on April 26, 2023. A Reimbursement Claim Form (Form) was submitted for the cameras and other equipment on September 11, 2023. The Form shows the County Sheriff requested the full $31,920; however, the County had only spent $9,581 from the grant fund towards the purchase. The reimbursement of $31,920 from the Indiana Department of Homeland Security was received on September 27, 2023. The fund had a balance of $22,339 as of December 31, 2023. As there are no grant expenditures for the remaining reimbursements received and the period of performance had ended, the County should have reimbursed the Indiana Department of Homeland Security $22,339. On May 9, 2023, the County Sheriff's grant administrator submitted a Program Report for the ILBC grant. The report was completed and submitted by the County Sheriff's grant administrator without a documented oversight or review process to ensure the completeness and accuracy of the report. The report incorrectly indicated that all expenditures had been completed. However, as of the date of the submission, the County had not purchased the body-worn cameras, and all federal funds had not been expended. The lack of internal controls and noncompliance were systemic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.302(b) states in part: "The financial management system of each non-Federal entity must provide for the following . . . (2) Accurate, current, and complete disclosure of the financial results of each Federal award or program in accordance with the reporting requirements set forth in §§ 200.328 and 200.329. . . ." 34 CFR 76.722 states: "A State may require a subgrantee to submit reports in a manner and format that assists the State in complying with the requirements under 34 CFR 76.720 and in carrying out other responsibilities under the program." INDIANA STATE BOARD OF ACCOUNTS 14 KOSCIUSKO COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) 2 CFR 200.344(d) states in part: "The non-Federal entity must promptly refund any balances of unobligated cash that the Federal awarding agency or pass-through entity paid in advance or paid and that are not authorized to be retained by the non-Federal entity for use in other projects. . . ." Cause A proper system of internal controls, which would include segregation of key functions, was not designed by management of the County to ensure the accuracy of the reimbursement invoice and the Program Report. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper design or implementation of the components of a system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As such, federal reimbursement was requested in excess of the amount spent. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County establish a proper system of internal controls, including policies and procedures that would provide segregation of duties to ensure appropriate reviews, approvals, and oversight are taking place to ensure reimbursement invoices are complete and accurate prior to submission. Furthermore, we recommended the County contact the awarding agency to discuss the funds remaining. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-001 Subject: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds - Reporting Federal Agency: Department of the Treasury Federal Program: COVID-19 - Coronavirus State and Local Fiscal Recovery Funds Assistance Listings Number: 21.027 Federal Award Number and Year (or Other Identifying Number): ILBC-2023-Body Camera-00052 Pass-Through Entity: Indiana Department of Homeland Security Compliance Requirement: Reporting Audit Findings: Material Weakness, Other Matters INDIANA STATE BOARD OF ACCOUNTS 13 KOSCIUSKO COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) Condition and Context The County Sheriff applied for the Indiana Local Body Camera Grant (ILBC). The grant is a reimbursable grant through the Indiana Department of Homeland Security. The County Sheriff was awarded this grant on January 1, 2023, with a grant cost amount of up to $31,920 to be spent from January 1, 2023 to December 31, 2023. The County Sheriff ordered body-worn cameras and other equipment on April 26, 2023. A Reimbursement Claim Form (Form) was submitted for the cameras and other equipment on September 11, 2023. The Form shows the County Sheriff requested the full $31,920; however, the County had only spent $9,581 from the grant fund towards the purchase. The reimbursement of $31,920 from the Indiana Department of Homeland Security was received on September 27, 2023. The fund had a balance of $22,339 as of December 31, 2023. As there are no grant expenditures for the remaining reimbursements received and the period of performance had ended, the County should have reimbursed the Indiana Department of Homeland Security $22,339. On May 9, 2023, the County Sheriff's grant administrator submitted a Program Report for the ILBC grant. The report was completed and submitted by the County Sheriff's grant administrator without a documented oversight or review process to ensure the completeness and accuracy of the report. The report incorrectly indicated that all expenditures had been completed. However, as of the date of the submission, the County had not purchased the body-worn cameras, and all federal funds had not been expended. The lack of internal controls and noncompliance were systemic issues throughout the audit period. Criteria 2 CFR 200.303 states in part: "The non-Federal entity must: (a) Establish and maintain effective internal control over the Federal award that provides reasonable assurance that the non-Federal entity is managing the Federal award in compliance with Federal statutes, regulations, and the terms and conditions of the Federal award. These internal controls should be in compliance with guidance in 'Standards for Internal Control in the Federal Government' issued by the Comptroller General of the United States or the 'Internal Control Integrated Framework', issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO). . . ." 2 CFR 200.302(b) states in part: "The financial management system of each non-Federal entity must provide for the following . . . (2) Accurate, current, and complete disclosure of the financial results of each Federal award or program in accordance with the reporting requirements set forth in §§ 200.328 and 200.329. . . ." 34 CFR 76.722 states: "A State may require a subgrantee to submit reports in a manner and format that assists the State in complying with the requirements under 34 CFR 76.720 and in carrying out other responsibilities under the program." INDIANA STATE BOARD OF ACCOUNTS 14 KOSCIUSKO COUNTY SCHEDULE OF FINDINGS AND QUESTIONED COSTS (Continued) 2 CFR 200.344(d) states in part: "The non-Federal entity must promptly refund any balances of unobligated cash that the Federal awarding agency or pass-through entity paid in advance or paid and that are not authorized to be retained by the non-Federal entity for use in other projects. . . ." Cause A proper system of internal controls, which would include segregation of key functions, was not designed by management of the County to ensure the accuracy of the reimbursement invoice and the Program Report. Embedded within a properly designed and implemented internal control system should be internal controls consisting of policies and procedures. Policies reflect the County's management statements of what should be done to effect internal controls, and procedures should consist of actions that would implement these policies. Effect Without the proper design or implementation of the components of a system of internal controls, including policies and procedures that provide segregation of duties and additional oversight as needed, the internal control system cannot be capable of effectively preventing, or detecting and correcting, material noncompliance. As such, federal reimbursement was requested in excess of the amount spent. Questioned Costs There were no questioned costs identified. Recommendation We recommended that management of the County establish a proper system of internal controls, including policies and procedures that would provide segregation of duties to ensure appropriate reviews, approvals, and oversight are taking place to ensure reimbursement invoices are complete and accurate prior to submission. Furthermore, we recommended the County contact the awarding agency to discuss the funds remaining. Views of Responsible Officials For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.