Audit 317135

FY End
2023-12-31
Total Expended
$13.10M
Findings
0
Programs
3
Organization: Port of Pasco (WA)
Year: 2023 Accepted: 2024-08-13

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
20.106 Airport Improvement Program $366,136 Yes 0
20.325 Consolidated Rail Infrastructure and Safety Improvements $103,161 - 0
20.205 Highway Planning and Construction $36 - 0

Contacts

Name Title Type
XHKDYX7HN4H8 Donna Watts Auditee
5095473378 Deborah O'Leary Auditor
No contacts on file

Notes to SEFA

Title: Program Costs Accounting Policies: This schedule is prepared on the same basis of accounting as the Port’s financial statements. The Port uses the full accrual basis of accounting. De Minimis Rate Used: N Rate Explanation: The Port has not elected to use the 10-percent de minimis indirect cost rate allowed under the Uniform Guidance. The amounts shown as current year expenditures represent only the federal grant portion of the program costs. Entire program costs, including the Port of Pasco’s portion, are more than shown. Such expenditures are recognized following the cost principles contained in Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, wherein certain types of expenditures are not allowable or are limited as to reimbursement.