Audit 315443

FY End
2023-12-31
Total Expended
$867,151
Findings
0
Programs
4
Year: 2023 Accepted: 2024-07-18

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
23.011 Appalachian Research, Technical Assistance, and Demonstration Projects $491,711 Yes 0
23.002 Appalachian Area Development $184,796 - 0
11.307 Economic Adjustment Assistance $70,000 - 0
66.454 Water Quality Management Planning $32,802 - 0

Contacts

Name Title Type
J7G5WFN1KEY5 Jennifer Gregory Auditee
6072879536 Ben Owens Auditor
No contacts on file

Notes to SEFA

Title: Basis of Presentation Accounting Policies: Basis of Presentation: The accompanying Schedule of Expenditures of Federal Awards presents the activity of all federal awards programs administered by Southern Tier East Regional Planning Development Board (d/b/a Southern Tier 8), an entity as defined in Note 1 to Southern Tier 8’s basic financial statements. Federal awards received directly from federal agencies, as well as federal awards passed through from other government agencies, are included on the Schedule of Expenditures of Federal Awards. Basis of Accounting:The basis of accounting varies by federal program consistent with the underlying regulations pertaining to each program. The information is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in, preparation of the financial statements. De Minimis Rate Used: N Rate Explanation: Indirect Costs: Indirect costs are included in the reported expenditures to the extent they are included in the federal financial reports used as the source for the data presented. Southern Tier 8 has elected not to use the 10% de minimus indirect cost rate. The accompanying Schedule of Expenditures of Federal Awards presents the activity of all federal awards programs administered by Southern Tier East Regional Planning Development Board (d/b/a Southern Tier 8), an entity as defined in Note 1 to Southern Tier 8’s basic financial statements. Federal awards received directly from federal agencies, as well as federal awards passed through from other government agencies, are included on the Schedule of Expenditures of Federal Awards.
Title: Basis of Accounting Accounting Policies: Basis of Presentation: The accompanying Schedule of Expenditures of Federal Awards presents the activity of all federal awards programs administered by Southern Tier East Regional Planning Development Board (d/b/a Southern Tier 8), an entity as defined in Note 1 to Southern Tier 8’s basic financial statements. Federal awards received directly from federal agencies, as well as federal awards passed through from other government agencies, are included on the Schedule of Expenditures of Federal Awards. Basis of Accounting:The basis of accounting varies by federal program consistent with the underlying regulations pertaining to each program. The information is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in, preparation of the financial statements. De Minimis Rate Used: N Rate Explanation: Indirect Costs: Indirect costs are included in the reported expenditures to the extent they are included in the federal financial reports used as the source for the data presented. Southern Tier 8 has elected not to use the 10% de minimus indirect cost rate. The basis of accounting varies by federal program consistent with the underlying regulations pertaining to each program. The information is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in, preparation of the financial statements.
Title: Allocation of Costs Accounting Policies: Basis of Presentation: The accompanying Schedule of Expenditures of Federal Awards presents the activity of all federal awards programs administered by Southern Tier East Regional Planning Development Board (d/b/a Southern Tier 8), an entity as defined in Note 1 to Southern Tier 8’s basic financial statements. Federal awards received directly from federal agencies, as well as federal awards passed through from other government agencies, are included on the Schedule of Expenditures of Federal Awards. Basis of Accounting:The basis of accounting varies by federal program consistent with the underlying regulations pertaining to each program. The information is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in, preparation of the financial statements. De Minimis Rate Used: N Rate Explanation: Indirect Costs: Indirect costs are included in the reported expenditures to the extent they are included in the federal financial reports used as the source for the data presented. Southern Tier 8 has elected not to use the 10% de minimus indirect cost rate. Costs have been allocated to programs based on a reasonable estimate of time spent on operating and loan administration. Loan administration expenses were allocated to the revolving loan funds based on the number of loans being serviced and the amount of work associated with the type of loan.
Title: Indirect Costs Accounting Policies: Basis of Presentation: The accompanying Schedule of Expenditures of Federal Awards presents the activity of all federal awards programs administered by Southern Tier East Regional Planning Development Board (d/b/a Southern Tier 8), an entity as defined in Note 1 to Southern Tier 8’s basic financial statements. Federal awards received directly from federal agencies, as well as federal awards passed through from other government agencies, are included on the Schedule of Expenditures of Federal Awards. Basis of Accounting:The basis of accounting varies by federal program consistent with the underlying regulations pertaining to each program. The information is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in, preparation of the financial statements. De Minimis Rate Used: N Rate Explanation: Indirect Costs: Indirect costs are included in the reported expenditures to the extent they are included in the federal financial reports used as the source for the data presented. Southern Tier 8 has elected not to use the 10% de minimus indirect cost rate. Indirect costs are included in the reported expenditures to the extent they are included in the federal financial reports used as the source for the data presented. Southern Tier 8 has elected not to use the 10% de minimus indirect cost rate.
Title: Matching Costs Accounting Policies: Basis of Presentation: The accompanying Schedule of Expenditures of Federal Awards presents the activity of all federal awards programs administered by Southern Tier East Regional Planning Development Board (d/b/a Southern Tier 8), an entity as defined in Note 1 to Southern Tier 8’s basic financial statements. Federal awards received directly from federal agencies, as well as federal awards passed through from other government agencies, are included on the Schedule of Expenditures of Federal Awards. Basis of Accounting:The basis of accounting varies by federal program consistent with the underlying regulations pertaining to each program. The information is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in, preparation of the financial statements. De Minimis Rate Used: N Rate Explanation: Indirect Costs: Indirect costs are included in the reported expenditures to the extent they are included in the federal financial reports used as the source for the data presented. Southern Tier 8 has elected not to use the 10% de minimus indirect cost rate. Matching costs, such as Southern Tier 8’s share of certain program costs, are not included in the reported expenditures.
Title: Other Disclosures Accounting Policies: Basis of Presentation: The accompanying Schedule of Expenditures of Federal Awards presents the activity of all federal awards programs administered by Southern Tier East Regional Planning Development Board (d/b/a Southern Tier 8), an entity as defined in Note 1 to Southern Tier 8’s basic financial statements. Federal awards received directly from federal agencies, as well as federal awards passed through from other government agencies, are included on the Schedule of Expenditures of Federal Awards. Basis of Accounting:The basis of accounting varies by federal program consistent with the underlying regulations pertaining to each program. The information is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in, preparation of the financial statements. De Minimis Rate Used: N Rate Explanation: Indirect Costs: Indirect costs are included in the reported expenditures to the extent they are included in the federal financial reports used as the source for the data presented. Southern Tier 8 has elected not to use the 10% de minimus indirect cost rate. No insurance is carried specifically to cover equipment purchased with federal funds. Any equipment purchased with federal funds has only a nominal value and is covered by Southern Tier 8’s casualty insurance policies. There were no loans or loan guarantees outstanding at year end.