Audit 309969

FY End
2023-12-31
Total Expended
$10.42M
Findings
0
Programs
1
Year: 2023 Accepted: 2024-06-26

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
20.106 Airport Improvement Program $3.93M Yes 0

Contacts

Name Title Type
K3RYTD92ET66 Mark Bishop Auditee
2319472250 Trina Ochs Auditor
No contacts on file

Notes to SEFA

Accounting Policies: 1. Basis of presentation - the accompanying schedule of expenditures of federal awards includes the grant activity of the Northwest Regional Airport Authority and is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with requirements of Title 2 U.S. Code of Federal Regulations Part 200, Cost Principles and Audit Requirements for Federal Awards ("Uniform Guidance"). Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in, the basic financial statements. 2. Management has reported that expenditures in the schedule of expenditures of federal awards are equal to or derived from amounts reported in the annual or final cost reports. Unallowed differences, if any, have been disclosed to the auditor. 3. The financial report including claims for advances and reimbursements and amounts claimed or used for matching, are timely, completed, accurate and contain information that is supported by the books and records from which the basic financial statements have been prepared. 4. The Authority did not use the 10% de-minimis cost rate under the Uniform Administrative Requirements. 5. A reconciliation of expenditures on the schedule of expenditures of federal awards and sources on the financial statement are as follows: Federal grants per statement of revenues, expenses and changes in net position $ 3,932,930 Federal capital contributions 6,490,402 Total federal expenditures per schedule of expenditures of federal awards $ 10,423,332 De Minimis Rate Used: N Rate Explanation: 4. The Authority did not use the 10% de-minimis cost rate under the Uniform Administrative Requirements.