Audit 307246

FY End
2023-06-30
Total Expended
$1.37M
Findings
2
Programs
13
Year: 2023 Accepted: 2024-05-27

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
398503 2023-009 Significant Deficiency Yes A
974945 2023-009 Significant Deficiency Yes A

Programs

Contacts

Name Title Type
LYBFHC93LVG6 Janice Duran Auditee
5755872502 Scott Eliason Auditor
No contacts on file

Notes to SEFA

Accounting Policies: The accompanying Schedule of Expenditures of Federal Awards (the Schedule) includes the federal award activity of Peñasco Independent School District (the District) under programs of the federal government for the year ended June 30, 2023. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR) Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the District, it is not intended to and does not present the financial position or changes in financial position of the District. Expenditures reported on the Schedule are reported on the modified accrual basis of accounting, which is the same basis as was used to prepare the fund financial statements. Such expenditures are recognized following the cost principles contained in the Uniform Guidance wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: During the year ended June 30, 2023, the New Mexico Public Education Department reimbursed the District for indirect costs at 7.78%.

Finding Details

2023-009 (2022-006) CONTROLS OVER PURCHASES - EDUCATIONAL STABILIZATION FUND GRANT (MODIFIED AND REPEATED) Federal Program Information Type of Finding: Significant Deficiency Compliance Areas: Allowable costs and allowable activities Assistance Listings Number: 84.425 Award Period: July 1, 2022 to June 30, 2023 Federal Agency: U.S. Department of Education, passed through the New Mexico Public Education Department Federal Award ID Number: 5425D210023 Program Name: Education Stabilization Fund Questioned Costs: None Condition We tested 25 operating disbursements and noted that one disbursement had the purchase order created after the vendor invoice was created. We also noted two of the invoices did not include written authorization to pay the invoice. Management’s Progress in 2023: Management did not make improvement over this condition from the prior year. Criteria New Mexico Public Education Department PSAB Supplement 13, Purchasing. Processing takes place after the purchase orders are created and approved. Vendor invoices are received and reviewed by the accounting department. The invoice is compared to the purchase order. Disbursement approval is separate of general ledger approval. Cause Management did not appropriately plan a certain purchase to ensure that a purchase order was in place at the start of the purchase. Management did not approve certain payments in writing. Effect The District is not in compliance with the New Mexico Public Education Department’s purchasing guidance.
2023-009 (2022-006) CONTROLS OVER PURCHASES - EDUCATIONAL STABILIZATION FUND GRANT (MODIFIED AND REPEATED) Federal Program Information Type of Finding: Significant Deficiency Compliance Areas: Allowable costs and allowable activities Assistance Listings Number: 84.425 Award Period: July 1, 2022 to June 30, 2023 Federal Agency: U.S. Department of Education, passed through the New Mexico Public Education Department Federal Award ID Number: 5425D210023 Program Name: Education Stabilization Fund Questioned Costs: None Condition We tested 25 operating disbursements and noted that one disbursement had the purchase order created after the vendor invoice was created. We also noted two of the invoices did not include written authorization to pay the invoice. Management’s Progress in 2023: Management did not make improvement over this condition from the prior year. Criteria New Mexico Public Education Department PSAB Supplement 13, Purchasing. Processing takes place after the purchase orders are created and approved. Vendor invoices are received and reviewed by the accounting department. The invoice is compared to the purchase order. Disbursement approval is separate of general ledger approval. Cause Management did not appropriately plan a certain purchase to ensure that a purchase order was in place at the start of the purchase. Management did not approve certain payments in writing. Effect The District is not in compliance with the New Mexico Public Education Department’s purchasing guidance.