FINDING 2023-001
Subject: COVID-19 - Education Stabilization Fund - Special Tests
and Provisions - Wage Rate Requirements
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Numbers: 84.245D, 84.425U
Federal Award Numbers and Years (or Other Identifying Numbers): S425D210013, S425U210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Special Tests and Provisions - Wage Rate Requirements
Audit Findings: Material Weakness, Modified Opinion
INDIANA STATE BOARD OF ACCOUNTS
13
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Condition and Context
Construction contracts in excess of $2,000 financed by federal assistance funds must pay wages
not less than those established for the locality of the project (prevailing wage rates) by the Department of
Labor (DOL) to their laborers and mechanics. Nonfederal entities are to include in their construction
contracts subject to the Wage Rate Requirements a provision that the contractor or subcontractor comply
with these requirements and the DOL regulations. This would include a requirement to submit a copy of
the payroll and statement of compliance to the entity for each week in which contract work was performed.
The School Corporation had not designed nor implemented a system of internal controls to ensure
that construction contracts in excess of $2,000 paid from federal grant funds included a prevailing wage
rate clause. There were two contracted vendors paid in excess of $2,000 with the COVID-19 - Education
Stabilization Fund grant award during the audit period for construction related projects. Both contracts,
totaling $2,296,300, were selected for testing. Neither of the contracts included the required prevailing
wage rate clause. In addition, certified payrolls were not submitted to the School Corporation by either
contractor.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
29 CFR 5.5 states in part:
"(a) The Agency head shall cause or require the contracting officer to insert in full in any
contract in excess of $2,000 which is entered into for the actual construction, alteration and/or
repair, including painting and decorating, of a public building or public work, or building or work
financed in whole or in part from Federal funds or in accordance with guarantees of a Federal
agency or financed from funds obtained by pledge of any contract of a Federal agency to make
a loan, grant or annual contribution (except where a different meaning is expressly indicated),
and which is subject to the labor standards provisions of any of the acts listed in § 5.1, the
following clauses . . .
(1) Minimum wages.
INDIANA STATE BOARD OF ACCOUNTS
14
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
(i) All laborers and mechanics employed or working upon the site of the work (or
under the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages
and bona fide fringe benefits (or cash equivalents thereof) due at time of payment
computed at rates not less than those contained in the wage determination of the
Secretary of Labor which is attached hereto and made a part hereof, regardless of any
contractual relationship which may be alleged to exist between the contractor and such
laborers and mechanics. . . .
(3) Payrolls and basic records. . . .
(ii)
(A) The contractor shall submit weekly for each week in which any contract work
is performed a copy of all payrolls to the (write in name of appropriate federal
agency) if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or
owner, as the case may be, for transmission to the (write in name of agency).
The payrolls submitted shall set out accurately and completely all of the
information required to be maintained under 29 CFR 5.5(a)(3)(i), except that
full social security numbers and home addresses shall not be included on
weekly transmittals. . . ."
2 CFR 200 Appendix II states in part:
"In addition to other provisions required by the Federal agency or non-Federal entity; all
contracts made by the non-Federal entity under the Federal award must contain provisions
covering the following, as applicable. . . .
(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal
program legislation, all prime construction contracts in excess of $2,000 awarded by non-
Federal entities must include a provision for compliance with the Davis-Bacon Act (40
U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations
(29 CFR Part 5, 'Labor Standards Provisions Applicable to Contracts Covering Federally
Financed and Assisted Construction'). In accordance with the statute, contractors must be
required to pay wages to laborers and mechanics at a rate not less than the prevailing
wages specified in a wage determination made by the Secretary of Labor. In addition,
contractors must be required to pay wages not less than once a week. . . ."
Cause
A proper system of internal controls was not designed by management of the School Corporation,
which would include segregation of key functions. Embedded within a properly designed and implemented
internal control system should be internal controls consisting of policies and procedures. Policies reflect
the School Corporation's management statements of what should be done to effect internal controls, and
procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS 15
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper implementation of an effectively designed system of internal controls, the
internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, construction contracts entered into did not contain the required wage rate
requirements clause nor were certified payrolls obtained by the School Corporation.
Noncompliance with the grant agreement and the compliance requirement could result in the loss
of future federal funds to the School Corporation
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure contracts have language including
prevailing wage rates and obtain payroll records to ensure wages are paid properly.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-001
Subject: COVID-19 - Education Stabilization Fund - Special Tests
and Provisions - Wage Rate Requirements
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Numbers: 84.245D, 84.425U
Federal Award Numbers and Years (or Other Identifying Numbers): S425D210013, S425U210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Special Tests and Provisions - Wage Rate Requirements
Audit Findings: Material Weakness, Modified Opinion
INDIANA STATE BOARD OF ACCOUNTS
13
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Condition and Context
Construction contracts in excess of $2,000 financed by federal assistance funds must pay wages
not less than those established for the locality of the project (prevailing wage rates) by the Department of
Labor (DOL) to their laborers and mechanics. Nonfederal entities are to include in their construction
contracts subject to the Wage Rate Requirements a provision that the contractor or subcontractor comply
with these requirements and the DOL regulations. This would include a requirement to submit a copy of
the payroll and statement of compliance to the entity for each week in which contract work was performed.
The School Corporation had not designed nor implemented a system of internal controls to ensure
that construction contracts in excess of $2,000 paid from federal grant funds included a prevailing wage
rate clause. There were two contracted vendors paid in excess of $2,000 with the COVID-19 - Education
Stabilization Fund grant award during the audit period for construction related projects. Both contracts,
totaling $2,296,300, were selected for testing. Neither of the contracts included the required prevailing
wage rate clause. In addition, certified payrolls were not submitted to the School Corporation by either
contractor.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
29 CFR 5.5 states in part:
"(a) The Agency head shall cause or require the contracting officer to insert in full in any
contract in excess of $2,000 which is entered into for the actual construction, alteration and/or
repair, including painting and decorating, of a public building or public work, or building or work
financed in whole or in part from Federal funds or in accordance with guarantees of a Federal
agency or financed from funds obtained by pledge of any contract of a Federal agency to make
a loan, grant or annual contribution (except where a different meaning is expressly indicated),
and which is subject to the labor standards provisions of any of the acts listed in § 5.1, the
following clauses . . .
(1) Minimum wages.
INDIANA STATE BOARD OF ACCOUNTS
14
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
(i) All laborers and mechanics employed or working upon the site of the work (or
under the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages
and bona fide fringe benefits (or cash equivalents thereof) due at time of payment
computed at rates not less than those contained in the wage determination of the
Secretary of Labor which is attached hereto and made a part hereof, regardless of any
contractual relationship which may be alleged to exist between the contractor and such
laborers and mechanics. . . .
(3) Payrolls and basic records. . . .
(ii)
(A) The contractor shall submit weekly for each week in which any contract work
is performed a copy of all payrolls to the (write in name of appropriate federal
agency) if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or
owner, as the case may be, for transmission to the (write in name of agency).
The payrolls submitted shall set out accurately and completely all of the
information required to be maintained under 29 CFR 5.5(a)(3)(i), except that
full social security numbers and home addresses shall not be included on
weekly transmittals. . . ."
2 CFR 200 Appendix II states in part:
"In addition to other provisions required by the Federal agency or non-Federal entity; all
contracts made by the non-Federal entity under the Federal award must contain provisions
covering the following, as applicable. . . .
(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal
program legislation, all prime construction contracts in excess of $2,000 awarded by non-
Federal entities must include a provision for compliance with the Davis-Bacon Act (40
U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations
(29 CFR Part 5, 'Labor Standards Provisions Applicable to Contracts Covering Federally
Financed and Assisted Construction'). In accordance with the statute, contractors must be
required to pay wages to laborers and mechanics at a rate not less than the prevailing
wages specified in a wage determination made by the Secretary of Labor. In addition,
contractors must be required to pay wages not less than once a week. . . ."
Cause
A proper system of internal controls was not designed by management of the School Corporation,
which would include segregation of key functions. Embedded within a properly designed and implemented
internal control system should be internal controls consisting of policies and procedures. Policies reflect
the School Corporation's management statements of what should be done to effect internal controls, and
procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS 15
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper implementation of an effectively designed system of internal controls, the
internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, construction contracts entered into did not contain the required wage rate
requirements clause nor were certified payrolls obtained by the School Corporation.
Noncompliance with the grant agreement and the compliance requirement could result in the loss
of future federal funds to the School Corporation
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure contracts have language including
prevailing wage rates and obtain payroll records to ensure wages are paid properly.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-001
Subject: COVID-19 - Education Stabilization Fund - Special Tests
and Provisions - Wage Rate Requirements
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Numbers: 84.245D, 84.425U
Federal Award Numbers and Years (or Other Identifying Numbers): S425D210013, S425U210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Special Tests and Provisions - Wage Rate Requirements
Audit Findings: Material Weakness, Modified Opinion
INDIANA STATE BOARD OF ACCOUNTS
13
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Condition and Context
Construction contracts in excess of $2,000 financed by federal assistance funds must pay wages
not less than those established for the locality of the project (prevailing wage rates) by the Department of
Labor (DOL) to their laborers and mechanics. Nonfederal entities are to include in their construction
contracts subject to the Wage Rate Requirements a provision that the contractor or subcontractor comply
with these requirements and the DOL regulations. This would include a requirement to submit a copy of
the payroll and statement of compliance to the entity for each week in which contract work was performed.
The School Corporation had not designed nor implemented a system of internal controls to ensure
that construction contracts in excess of $2,000 paid from federal grant funds included a prevailing wage
rate clause. There were two contracted vendors paid in excess of $2,000 with the COVID-19 - Education
Stabilization Fund grant award during the audit period for construction related projects. Both contracts,
totaling $2,296,300, were selected for testing. Neither of the contracts included the required prevailing
wage rate clause. In addition, certified payrolls were not submitted to the School Corporation by either
contractor.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
29 CFR 5.5 states in part:
"(a) The Agency head shall cause or require the contracting officer to insert in full in any
contract in excess of $2,000 which is entered into for the actual construction, alteration and/or
repair, including painting and decorating, of a public building or public work, or building or work
financed in whole or in part from Federal funds or in accordance with guarantees of a Federal
agency or financed from funds obtained by pledge of any contract of a Federal agency to make
a loan, grant or annual contribution (except where a different meaning is expressly indicated),
and which is subject to the labor standards provisions of any of the acts listed in § 5.1, the
following clauses . . .
(1) Minimum wages.
INDIANA STATE BOARD OF ACCOUNTS
14
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
(i) All laborers and mechanics employed or working upon the site of the work (or
under the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages
and bona fide fringe benefits (or cash equivalents thereof) due at time of payment
computed at rates not less than those contained in the wage determination of the
Secretary of Labor which is attached hereto and made a part hereof, regardless of any
contractual relationship which may be alleged to exist between the contractor and such
laborers and mechanics. . . .
(3) Payrolls and basic records. . . .
(ii)
(A) The contractor shall submit weekly for each week in which any contract work
is performed a copy of all payrolls to the (write in name of appropriate federal
agency) if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or
owner, as the case may be, for transmission to the (write in name of agency).
The payrolls submitted shall set out accurately and completely all of the
information required to be maintained under 29 CFR 5.5(a)(3)(i), except that
full social security numbers and home addresses shall not be included on
weekly transmittals. . . ."
2 CFR 200 Appendix II states in part:
"In addition to other provisions required by the Federal agency or non-Federal entity; all
contracts made by the non-Federal entity under the Federal award must contain provisions
covering the following, as applicable. . . .
(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal
program legislation, all prime construction contracts in excess of $2,000 awarded by non-
Federal entities must include a provision for compliance with the Davis-Bacon Act (40
U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations
(29 CFR Part 5, 'Labor Standards Provisions Applicable to Contracts Covering Federally
Financed and Assisted Construction'). In accordance with the statute, contractors must be
required to pay wages to laborers and mechanics at a rate not less than the prevailing
wages specified in a wage determination made by the Secretary of Labor. In addition,
contractors must be required to pay wages not less than once a week. . . ."
Cause
A proper system of internal controls was not designed by management of the School Corporation,
which would include segregation of key functions. Embedded within a properly designed and implemented
internal control system should be internal controls consisting of policies and procedures. Policies reflect
the School Corporation's management statements of what should be done to effect internal controls, and
procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS 15
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper implementation of an effectively designed system of internal controls, the
internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, construction contracts entered into did not contain the required wage rate
requirements clause nor were certified payrolls obtained by the School Corporation.
Noncompliance with the grant agreement and the compliance requirement could result in the loss
of future federal funds to the School Corporation
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure contracts have language including
prevailing wage rates and obtain payroll records to ensure wages are paid properly.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-001
Subject: COVID-19 - Education Stabilization Fund - Special Tests
and Provisions - Wage Rate Requirements
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Numbers: 84.245D, 84.425U
Federal Award Numbers and Years (or Other Identifying Numbers): S425D210013, S425U210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Special Tests and Provisions - Wage Rate Requirements
Audit Findings: Material Weakness, Modified Opinion
INDIANA STATE BOARD OF ACCOUNTS
13
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Condition and Context
Construction contracts in excess of $2,000 financed by federal assistance funds must pay wages
not less than those established for the locality of the project (prevailing wage rates) by the Department of
Labor (DOL) to their laborers and mechanics. Nonfederal entities are to include in their construction
contracts subject to the Wage Rate Requirements a provision that the contractor or subcontractor comply
with these requirements and the DOL regulations. This would include a requirement to submit a copy of
the payroll and statement of compliance to the entity for each week in which contract work was performed.
The School Corporation had not designed nor implemented a system of internal controls to ensure
that construction contracts in excess of $2,000 paid from federal grant funds included a prevailing wage
rate clause. There were two contracted vendors paid in excess of $2,000 with the COVID-19 - Education
Stabilization Fund grant award during the audit period for construction related projects. Both contracts,
totaling $2,296,300, were selected for testing. Neither of the contracts included the required prevailing
wage rate clause. In addition, certified payrolls were not submitted to the School Corporation by either
contractor.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
29 CFR 5.5 states in part:
"(a) The Agency head shall cause or require the contracting officer to insert in full in any
contract in excess of $2,000 which is entered into for the actual construction, alteration and/or
repair, including painting and decorating, of a public building or public work, or building or work
financed in whole or in part from Federal funds or in accordance with guarantees of a Federal
agency or financed from funds obtained by pledge of any contract of a Federal agency to make
a loan, grant or annual contribution (except where a different meaning is expressly indicated),
and which is subject to the labor standards provisions of any of the acts listed in § 5.1, the
following clauses . . .
(1) Minimum wages.
INDIANA STATE BOARD OF ACCOUNTS
14
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
(i) All laborers and mechanics employed or working upon the site of the work (or
under the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages
and bona fide fringe benefits (or cash equivalents thereof) due at time of payment
computed at rates not less than those contained in the wage determination of the
Secretary of Labor which is attached hereto and made a part hereof, regardless of any
contractual relationship which may be alleged to exist between the contractor and such
laborers and mechanics. . . .
(3) Payrolls and basic records. . . .
(ii)
(A) The contractor shall submit weekly for each week in which any contract work
is performed a copy of all payrolls to the (write in name of appropriate federal
agency) if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or
owner, as the case may be, for transmission to the (write in name of agency).
The payrolls submitted shall set out accurately and completely all of the
information required to be maintained under 29 CFR 5.5(a)(3)(i), except that
full social security numbers and home addresses shall not be included on
weekly transmittals. . . ."
2 CFR 200 Appendix II states in part:
"In addition to other provisions required by the Federal agency or non-Federal entity; all
contracts made by the non-Federal entity under the Federal award must contain provisions
covering the following, as applicable. . . .
(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal
program legislation, all prime construction contracts in excess of $2,000 awarded by non-
Federal entities must include a provision for compliance with the Davis-Bacon Act (40
U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations
(29 CFR Part 5, 'Labor Standards Provisions Applicable to Contracts Covering Federally
Financed and Assisted Construction'). In accordance with the statute, contractors must be
required to pay wages to laborers and mechanics at a rate not less than the prevailing
wages specified in a wage determination made by the Secretary of Labor. In addition,
contractors must be required to pay wages not less than once a week. . . ."
Cause
A proper system of internal controls was not designed by management of the School Corporation,
which would include segregation of key functions. Embedded within a properly designed and implemented
internal control system should be internal controls consisting of policies and procedures. Policies reflect
the School Corporation's management statements of what should be done to effect internal controls, and
procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS 15
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper implementation of an effectively designed system of internal controls, the
internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, construction contracts entered into did not contain the required wage rate
requirements clause nor were certified payrolls obtained by the School Corporation.
Noncompliance with the grant agreement and the compliance requirement could result in the loss
of future federal funds to the School Corporation
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure contracts have language including
prevailing wage rates and obtain payroll records to ensure wages are paid properly.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-002
Subject: COVID-19 - Education Stabilization Fund - Reporting
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Number: 84.425D
Federal Award Number and Year (or Other Identifying Number): S425D210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Reporting
Audit Findings: Material Weakness, Other Matters
Condition and Context
The School Corporation had not properly designed or implemented a system of internal controls,
which would include appropriate segregation of duties, that would likely be effective in preventing, or
detecting and correcting, noncompliance.
The School Corporation was required to submit annual data reports to the Indiana Department of
Education via JotForm, a form/report builder. Data to be submitted included, but was not limited to, current
period expenditures, prior period expenditures, and expenditures per activity.
During the audit period the School Corporation submitted one ESSER I report, two ESSER II
reports, and two ESSER III reports, for a total of five reports. Although the Treasurer prepared the annual
data collection report, and the ESSER Program Director or Assistant Superintendent of Schools, both of
whom are knowledgeable about the program, reviewed and approved the report prior to submission, the
internal control was not effective and did not prevent, or detect and correct, errors prior to submission.
INDIANA STATE BOARD OF ACCOUNTS 16
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
All five reports were selected for testing. Neither of the ESSER II annual data reports were
accurately supported by the School Corporation's records. The errors identified were as follows:
The ESSER II, Year 1 report, which covered the period of July 1, 2020 to June 30, 2021,
reported total expenses of $58,917; however, the School Corporation's ledger for the same
period had total expenses of $1,306.
The ESSER II, Year 2 report, which covered the period of July 1, 2021 to June 30, 2022,
reported total expenses of $60,441; however, the School Corporation's ledger for the same
period had total expenses of $63,565.
The lack of effective internal controls and noncompliance were isolated to the S425D210013 grant
award.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
2 CFR 200.302(b) states in part:
"The financial management system of each non-Federal entity must provide for the following
. . .
(2) Accurate, current, and complete disclosure of the financial results of each Federal
award or program in accordance with the reporting requirements set forth in §§ 200.328
and 200.329. . . ."
34 CFR 76.722 states: "A State may require a subgrantee to submit reports in a manner and format
that assists the State in complying with the requirements under 34 CFR 76.720 and in carrying out other
responsibilities under the program."
34 CFR 76.731 states: "A State and a subgrantee shall keep records to show its compliance with
program requirements."
Cause
A proper system of internal controls was not designed and implemented by management of the
School Corporation which would include segregation of key functions. Embedded within a properly
designed and implemented internal control system should be internal controls consisting of policies and
procedures. Policies reflect the School Corporation's management statements of what should be done to
effect internal controls, and procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS
17
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper design or implementation of the components of a system of internal controls,
including policies and procedures that provide segregation of duties and additional oversight as needed,
the internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, the reports were not supported by the School Corporation's underlying
accounting records.
Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of
the federal award could result in the loss of future federal funding to the School Corporation.
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure all reports submitted on behalf of the
COVID-19 - Education Stabilization Fund program are supported by the School Corporation's underlying
accounting records.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-002
Subject: COVID-19 - Education Stabilization Fund - Reporting
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Number: 84.425D
Federal Award Number and Year (or Other Identifying Number): S425D210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Reporting
Audit Findings: Material Weakness, Other Matters
Condition and Context
The School Corporation had not properly designed or implemented a system of internal controls,
which would include appropriate segregation of duties, that would likely be effective in preventing, or
detecting and correcting, noncompliance.
The School Corporation was required to submit annual data reports to the Indiana Department of
Education via JotForm, a form/report builder. Data to be submitted included, but was not limited to, current
period expenditures, prior period expenditures, and expenditures per activity.
During the audit period the School Corporation submitted one ESSER I report, two ESSER II
reports, and two ESSER III reports, for a total of five reports. Although the Treasurer prepared the annual
data collection report, and the ESSER Program Director or Assistant Superintendent of Schools, both of
whom are knowledgeable about the program, reviewed and approved the report prior to submission, the
internal control was not effective and did not prevent, or detect and correct, errors prior to submission.
INDIANA STATE BOARD OF ACCOUNTS 16
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
All five reports were selected for testing. Neither of the ESSER II annual data reports were
accurately supported by the School Corporation's records. The errors identified were as follows:
The ESSER II, Year 1 report, which covered the period of July 1, 2020 to June 30, 2021,
reported total expenses of $58,917; however, the School Corporation's ledger for the same
period had total expenses of $1,306.
The ESSER II, Year 2 report, which covered the period of July 1, 2021 to June 30, 2022,
reported total expenses of $60,441; however, the School Corporation's ledger for the same
period had total expenses of $63,565.
The lack of effective internal controls and noncompliance were isolated to the S425D210013 grant
award.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
2 CFR 200.302(b) states in part:
"The financial management system of each non-Federal entity must provide for the following
. . .
(2) Accurate, current, and complete disclosure of the financial results of each Federal
award or program in accordance with the reporting requirements set forth in §§ 200.328
and 200.329. . . ."
34 CFR 76.722 states: "A State may require a subgrantee to submit reports in a manner and format
that assists the State in complying with the requirements under 34 CFR 76.720 and in carrying out other
responsibilities under the program."
34 CFR 76.731 states: "A State and a subgrantee shall keep records to show its compliance with
program requirements."
Cause
A proper system of internal controls was not designed and implemented by management of the
School Corporation which would include segregation of key functions. Embedded within a properly
designed and implemented internal control system should be internal controls consisting of policies and
procedures. Policies reflect the School Corporation's management statements of what should be done to
effect internal controls, and procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS
17
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper design or implementation of the components of a system of internal controls,
including policies and procedures that provide segregation of duties and additional oversight as needed,
the internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, the reports were not supported by the School Corporation's underlying
accounting records.
Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of
the federal award could result in the loss of future federal funding to the School Corporation.
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure all reports submitted on behalf of the
COVID-19 - Education Stabilization Fund program are supported by the School Corporation's underlying
accounting records.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-001
Subject: COVID-19 - Education Stabilization Fund - Special Tests
and Provisions - Wage Rate Requirements
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Numbers: 84.245D, 84.425U
Federal Award Numbers and Years (or Other Identifying Numbers): S425D210013, S425U210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Special Tests and Provisions - Wage Rate Requirements
Audit Findings: Material Weakness, Modified Opinion
INDIANA STATE BOARD OF ACCOUNTS
13
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Condition and Context
Construction contracts in excess of $2,000 financed by federal assistance funds must pay wages
not less than those established for the locality of the project (prevailing wage rates) by the Department of
Labor (DOL) to their laborers and mechanics. Nonfederal entities are to include in their construction
contracts subject to the Wage Rate Requirements a provision that the contractor or subcontractor comply
with these requirements and the DOL regulations. This would include a requirement to submit a copy of
the payroll and statement of compliance to the entity for each week in which contract work was performed.
The School Corporation had not designed nor implemented a system of internal controls to ensure
that construction contracts in excess of $2,000 paid from federal grant funds included a prevailing wage
rate clause. There were two contracted vendors paid in excess of $2,000 with the COVID-19 - Education
Stabilization Fund grant award during the audit period for construction related projects. Both contracts,
totaling $2,296,300, were selected for testing. Neither of the contracts included the required prevailing
wage rate clause. In addition, certified payrolls were not submitted to the School Corporation by either
contractor.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
29 CFR 5.5 states in part:
"(a) The Agency head shall cause or require the contracting officer to insert in full in any
contract in excess of $2,000 which is entered into for the actual construction, alteration and/or
repair, including painting and decorating, of a public building or public work, or building or work
financed in whole or in part from Federal funds or in accordance with guarantees of a Federal
agency or financed from funds obtained by pledge of any contract of a Federal agency to make
a loan, grant or annual contribution (except where a different meaning is expressly indicated),
and which is subject to the labor standards provisions of any of the acts listed in § 5.1, the
following clauses . . .
(1) Minimum wages.
INDIANA STATE BOARD OF ACCOUNTS
14
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
(i) All laborers and mechanics employed or working upon the site of the work (or
under the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages
and bona fide fringe benefits (or cash equivalents thereof) due at time of payment
computed at rates not less than those contained in the wage determination of the
Secretary of Labor which is attached hereto and made a part hereof, regardless of any
contractual relationship which may be alleged to exist between the contractor and such
laborers and mechanics. . . .
(3) Payrolls and basic records. . . .
(ii)
(A) The contractor shall submit weekly for each week in which any contract work
is performed a copy of all payrolls to the (write in name of appropriate federal
agency) if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or
owner, as the case may be, for transmission to the (write in name of agency).
The payrolls submitted shall set out accurately and completely all of the
information required to be maintained under 29 CFR 5.5(a)(3)(i), except that
full social security numbers and home addresses shall not be included on
weekly transmittals. . . ."
2 CFR 200 Appendix II states in part:
"In addition to other provisions required by the Federal agency or non-Federal entity; all
contracts made by the non-Federal entity under the Federal award must contain provisions
covering the following, as applicable. . . .
(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal
program legislation, all prime construction contracts in excess of $2,000 awarded by non-
Federal entities must include a provision for compliance with the Davis-Bacon Act (40
U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations
(29 CFR Part 5, 'Labor Standards Provisions Applicable to Contracts Covering Federally
Financed and Assisted Construction'). In accordance with the statute, contractors must be
required to pay wages to laborers and mechanics at a rate not less than the prevailing
wages specified in a wage determination made by the Secretary of Labor. In addition,
contractors must be required to pay wages not less than once a week. . . ."
Cause
A proper system of internal controls was not designed by management of the School Corporation,
which would include segregation of key functions. Embedded within a properly designed and implemented
internal control system should be internal controls consisting of policies and procedures. Policies reflect
the School Corporation's management statements of what should be done to effect internal controls, and
procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS 15
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper implementation of an effectively designed system of internal controls, the
internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, construction contracts entered into did not contain the required wage rate
requirements clause nor were certified payrolls obtained by the School Corporation.
Noncompliance with the grant agreement and the compliance requirement could result in the loss
of future federal funds to the School Corporation
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure contracts have language including
prevailing wage rates and obtain payroll records to ensure wages are paid properly.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-001
Subject: COVID-19 - Education Stabilization Fund - Special Tests
and Provisions - Wage Rate Requirements
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Numbers: 84.245D, 84.425U
Federal Award Numbers and Years (or Other Identifying Numbers): S425D210013, S425U210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Special Tests and Provisions - Wage Rate Requirements
Audit Findings: Material Weakness, Modified Opinion
INDIANA STATE BOARD OF ACCOUNTS
13
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Condition and Context
Construction contracts in excess of $2,000 financed by federal assistance funds must pay wages
not less than those established for the locality of the project (prevailing wage rates) by the Department of
Labor (DOL) to their laborers and mechanics. Nonfederal entities are to include in their construction
contracts subject to the Wage Rate Requirements a provision that the contractor or subcontractor comply
with these requirements and the DOL regulations. This would include a requirement to submit a copy of
the payroll and statement of compliance to the entity for each week in which contract work was performed.
The School Corporation had not designed nor implemented a system of internal controls to ensure
that construction contracts in excess of $2,000 paid from federal grant funds included a prevailing wage
rate clause. There were two contracted vendors paid in excess of $2,000 with the COVID-19 - Education
Stabilization Fund grant award during the audit period for construction related projects. Both contracts,
totaling $2,296,300, were selected for testing. Neither of the contracts included the required prevailing
wage rate clause. In addition, certified payrolls were not submitted to the School Corporation by either
contractor.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
29 CFR 5.5 states in part:
"(a) The Agency head shall cause or require the contracting officer to insert in full in any
contract in excess of $2,000 which is entered into for the actual construction, alteration and/or
repair, including painting and decorating, of a public building or public work, or building or work
financed in whole or in part from Federal funds or in accordance with guarantees of a Federal
agency or financed from funds obtained by pledge of any contract of a Federal agency to make
a loan, grant or annual contribution (except where a different meaning is expressly indicated),
and which is subject to the labor standards provisions of any of the acts listed in § 5.1, the
following clauses . . .
(1) Minimum wages.
INDIANA STATE BOARD OF ACCOUNTS
14
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
(i) All laborers and mechanics employed or working upon the site of the work (or
under the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages
and bona fide fringe benefits (or cash equivalents thereof) due at time of payment
computed at rates not less than those contained in the wage determination of the
Secretary of Labor which is attached hereto and made a part hereof, regardless of any
contractual relationship which may be alleged to exist between the contractor and such
laborers and mechanics. . . .
(3) Payrolls and basic records. . . .
(ii)
(A) The contractor shall submit weekly for each week in which any contract work
is performed a copy of all payrolls to the (write in name of appropriate federal
agency) if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or
owner, as the case may be, for transmission to the (write in name of agency).
The payrolls submitted shall set out accurately and completely all of the
information required to be maintained under 29 CFR 5.5(a)(3)(i), except that
full social security numbers and home addresses shall not be included on
weekly transmittals. . . ."
2 CFR 200 Appendix II states in part:
"In addition to other provisions required by the Federal agency or non-Federal entity; all
contracts made by the non-Federal entity under the Federal award must contain provisions
covering the following, as applicable. . . .
(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal
program legislation, all prime construction contracts in excess of $2,000 awarded by non-
Federal entities must include a provision for compliance with the Davis-Bacon Act (40
U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations
(29 CFR Part 5, 'Labor Standards Provisions Applicable to Contracts Covering Federally
Financed and Assisted Construction'). In accordance with the statute, contractors must be
required to pay wages to laborers and mechanics at a rate not less than the prevailing
wages specified in a wage determination made by the Secretary of Labor. In addition,
contractors must be required to pay wages not less than once a week. . . ."
Cause
A proper system of internal controls was not designed by management of the School Corporation,
which would include segregation of key functions. Embedded within a properly designed and implemented
internal control system should be internal controls consisting of policies and procedures. Policies reflect
the School Corporation's management statements of what should be done to effect internal controls, and
procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS 15
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper implementation of an effectively designed system of internal controls, the
internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, construction contracts entered into did not contain the required wage rate
requirements clause nor were certified payrolls obtained by the School Corporation.
Noncompliance with the grant agreement and the compliance requirement could result in the loss
of future federal funds to the School Corporation
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure contracts have language including
prevailing wage rates and obtain payroll records to ensure wages are paid properly.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-001
Subject: COVID-19 - Education Stabilization Fund - Special Tests
and Provisions - Wage Rate Requirements
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Numbers: 84.245D, 84.425U
Federal Award Numbers and Years (or Other Identifying Numbers): S425D210013, S425U210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Special Tests and Provisions - Wage Rate Requirements
Audit Findings: Material Weakness, Modified Opinion
INDIANA STATE BOARD OF ACCOUNTS
13
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Condition and Context
Construction contracts in excess of $2,000 financed by federal assistance funds must pay wages
not less than those established for the locality of the project (prevailing wage rates) by the Department of
Labor (DOL) to their laborers and mechanics. Nonfederal entities are to include in their construction
contracts subject to the Wage Rate Requirements a provision that the contractor or subcontractor comply
with these requirements and the DOL regulations. This would include a requirement to submit a copy of
the payroll and statement of compliance to the entity for each week in which contract work was performed.
The School Corporation had not designed nor implemented a system of internal controls to ensure
that construction contracts in excess of $2,000 paid from federal grant funds included a prevailing wage
rate clause. There were two contracted vendors paid in excess of $2,000 with the COVID-19 - Education
Stabilization Fund grant award during the audit period for construction related projects. Both contracts,
totaling $2,296,300, were selected for testing. Neither of the contracts included the required prevailing
wage rate clause. In addition, certified payrolls were not submitted to the School Corporation by either
contractor.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
29 CFR 5.5 states in part:
"(a) The Agency head shall cause or require the contracting officer to insert in full in any
contract in excess of $2,000 which is entered into for the actual construction, alteration and/or
repair, including painting and decorating, of a public building or public work, or building or work
financed in whole or in part from Federal funds or in accordance with guarantees of a Federal
agency or financed from funds obtained by pledge of any contract of a Federal agency to make
a loan, grant or annual contribution (except where a different meaning is expressly indicated),
and which is subject to the labor standards provisions of any of the acts listed in § 5.1, the
following clauses . . .
(1) Minimum wages.
INDIANA STATE BOARD OF ACCOUNTS
14
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
(i) All laborers and mechanics employed or working upon the site of the work (or
under the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages
and bona fide fringe benefits (or cash equivalents thereof) due at time of payment
computed at rates not less than those contained in the wage determination of the
Secretary of Labor which is attached hereto and made a part hereof, regardless of any
contractual relationship which may be alleged to exist between the contractor and such
laborers and mechanics. . . .
(3) Payrolls and basic records. . . .
(ii)
(A) The contractor shall submit weekly for each week in which any contract work
is performed a copy of all payrolls to the (write in name of appropriate federal
agency) if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or
owner, as the case may be, for transmission to the (write in name of agency).
The payrolls submitted shall set out accurately and completely all of the
information required to be maintained under 29 CFR 5.5(a)(3)(i), except that
full social security numbers and home addresses shall not be included on
weekly transmittals. . . ."
2 CFR 200 Appendix II states in part:
"In addition to other provisions required by the Federal agency or non-Federal entity; all
contracts made by the non-Federal entity under the Federal award must contain provisions
covering the following, as applicable. . . .
(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal
program legislation, all prime construction contracts in excess of $2,000 awarded by non-
Federal entities must include a provision for compliance with the Davis-Bacon Act (40
U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations
(29 CFR Part 5, 'Labor Standards Provisions Applicable to Contracts Covering Federally
Financed and Assisted Construction'). In accordance with the statute, contractors must be
required to pay wages to laborers and mechanics at a rate not less than the prevailing
wages specified in a wage determination made by the Secretary of Labor. In addition,
contractors must be required to pay wages not less than once a week. . . ."
Cause
A proper system of internal controls was not designed by management of the School Corporation,
which would include segregation of key functions. Embedded within a properly designed and implemented
internal control system should be internal controls consisting of policies and procedures. Policies reflect
the School Corporation's management statements of what should be done to effect internal controls, and
procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS 15
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper implementation of an effectively designed system of internal controls, the
internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, construction contracts entered into did not contain the required wage rate
requirements clause nor were certified payrolls obtained by the School Corporation.
Noncompliance with the grant agreement and the compliance requirement could result in the loss
of future federal funds to the School Corporation
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure contracts have language including
prevailing wage rates and obtain payroll records to ensure wages are paid properly.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-001
Subject: COVID-19 - Education Stabilization Fund - Special Tests
and Provisions - Wage Rate Requirements
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Numbers: 84.245D, 84.425U
Federal Award Numbers and Years (or Other Identifying Numbers): S425D210013, S425U210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Special Tests and Provisions - Wage Rate Requirements
Audit Findings: Material Weakness, Modified Opinion
INDIANA STATE BOARD OF ACCOUNTS
13
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Condition and Context
Construction contracts in excess of $2,000 financed by federal assistance funds must pay wages
not less than those established for the locality of the project (prevailing wage rates) by the Department of
Labor (DOL) to their laborers and mechanics. Nonfederal entities are to include in their construction
contracts subject to the Wage Rate Requirements a provision that the contractor or subcontractor comply
with these requirements and the DOL regulations. This would include a requirement to submit a copy of
the payroll and statement of compliance to the entity for each week in which contract work was performed.
The School Corporation had not designed nor implemented a system of internal controls to ensure
that construction contracts in excess of $2,000 paid from federal grant funds included a prevailing wage
rate clause. There were two contracted vendors paid in excess of $2,000 with the COVID-19 - Education
Stabilization Fund grant award during the audit period for construction related projects. Both contracts,
totaling $2,296,300, were selected for testing. Neither of the contracts included the required prevailing
wage rate clause. In addition, certified payrolls were not submitted to the School Corporation by either
contractor.
The lack of internal controls and noncompliance were systemic issues throughout the audit period.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
29 CFR 5.5 states in part:
"(a) The Agency head shall cause or require the contracting officer to insert in full in any
contract in excess of $2,000 which is entered into for the actual construction, alteration and/or
repair, including painting and decorating, of a public building or public work, or building or work
financed in whole or in part from Federal funds or in accordance with guarantees of a Federal
agency or financed from funds obtained by pledge of any contract of a Federal agency to make
a loan, grant or annual contribution (except where a different meaning is expressly indicated),
and which is subject to the labor standards provisions of any of the acts listed in § 5.1, the
following clauses . . .
(1) Minimum wages.
INDIANA STATE BOARD OF ACCOUNTS
14
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
(i) All laborers and mechanics employed or working upon the site of the work (or
under the United States Housing Act of 1937 or under the Housing Act of 1949 in the
construction or development of the project), will be paid unconditionally and not less
often than once a week, and without subsequent deduction or rebate on any account
(except such payroll deductions as are permitted by regulations issued by the
Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages
and bona fide fringe benefits (or cash equivalents thereof) due at time of payment
computed at rates not less than those contained in the wage determination of the
Secretary of Labor which is attached hereto and made a part hereof, regardless of any
contractual relationship which may be alleged to exist between the contractor and such
laborers and mechanics. . . .
(3) Payrolls and basic records. . . .
(ii)
(A) The contractor shall submit weekly for each week in which any contract work
is performed a copy of all payrolls to the (write in name of appropriate federal
agency) if the agency is a party to the contract, but if the agency is not such a
party, the contractor will submit the payrolls to the applicant, sponsor, or
owner, as the case may be, for transmission to the (write in name of agency).
The payrolls submitted shall set out accurately and completely all of the
information required to be maintained under 29 CFR 5.5(a)(3)(i), except that
full social security numbers and home addresses shall not be included on
weekly transmittals. . . ."
2 CFR 200 Appendix II states in part:
"In addition to other provisions required by the Federal agency or non-Federal entity; all
contracts made by the non-Federal entity under the Federal award must contain provisions
covering the following, as applicable. . . .
(D) Davis-Bacon Act, as amended (40 U.S.C. 3141-3148). When required by Federal
program legislation, all prime construction contracts in excess of $2,000 awarded by non-
Federal entities must include a provision for compliance with the Davis-Bacon Act (40
U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations
(29 CFR Part 5, 'Labor Standards Provisions Applicable to Contracts Covering Federally
Financed and Assisted Construction'). In accordance with the statute, contractors must be
required to pay wages to laborers and mechanics at a rate not less than the prevailing
wages specified in a wage determination made by the Secretary of Labor. In addition,
contractors must be required to pay wages not less than once a week. . . ."
Cause
A proper system of internal controls was not designed by management of the School Corporation,
which would include segregation of key functions. Embedded within a properly designed and implemented
internal control system should be internal controls consisting of policies and procedures. Policies reflect
the School Corporation's management statements of what should be done to effect internal controls, and
procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS 15
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper implementation of an effectively designed system of internal controls, the
internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, construction contracts entered into did not contain the required wage rate
requirements clause nor were certified payrolls obtained by the School Corporation.
Noncompliance with the grant agreement and the compliance requirement could result in the loss
of future federal funds to the School Corporation
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure contracts have language including
prevailing wage rates and obtain payroll records to ensure wages are paid properly.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-002
Subject: COVID-19 - Education Stabilization Fund - Reporting
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Number: 84.425D
Federal Award Number and Year (or Other Identifying Number): S425D210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Reporting
Audit Findings: Material Weakness, Other Matters
Condition and Context
The School Corporation had not properly designed or implemented a system of internal controls,
which would include appropriate segregation of duties, that would likely be effective in preventing, or
detecting and correcting, noncompliance.
The School Corporation was required to submit annual data reports to the Indiana Department of
Education via JotForm, a form/report builder. Data to be submitted included, but was not limited to, current
period expenditures, prior period expenditures, and expenditures per activity.
During the audit period the School Corporation submitted one ESSER I report, two ESSER II
reports, and two ESSER III reports, for a total of five reports. Although the Treasurer prepared the annual
data collection report, and the ESSER Program Director or Assistant Superintendent of Schools, both of
whom are knowledgeable about the program, reviewed and approved the report prior to submission, the
internal control was not effective and did not prevent, or detect and correct, errors prior to submission.
INDIANA STATE BOARD OF ACCOUNTS 16
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
All five reports were selected for testing. Neither of the ESSER II annual data reports were
accurately supported by the School Corporation's records. The errors identified were as follows:
The ESSER II, Year 1 report, which covered the period of July 1, 2020 to June 30, 2021,
reported total expenses of $58,917; however, the School Corporation's ledger for the same
period had total expenses of $1,306.
The ESSER II, Year 2 report, which covered the period of July 1, 2021 to June 30, 2022,
reported total expenses of $60,441; however, the School Corporation's ledger for the same
period had total expenses of $63,565.
The lack of effective internal controls and noncompliance were isolated to the S425D210013 grant
award.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
2 CFR 200.302(b) states in part:
"The financial management system of each non-Federal entity must provide for the following
. . .
(2) Accurate, current, and complete disclosure of the financial results of each Federal
award or program in accordance with the reporting requirements set forth in §§ 200.328
and 200.329. . . ."
34 CFR 76.722 states: "A State may require a subgrantee to submit reports in a manner and format
that assists the State in complying with the requirements under 34 CFR 76.720 and in carrying out other
responsibilities under the program."
34 CFR 76.731 states: "A State and a subgrantee shall keep records to show its compliance with
program requirements."
Cause
A proper system of internal controls was not designed and implemented by management of the
School Corporation which would include segregation of key functions. Embedded within a properly
designed and implemented internal control system should be internal controls consisting of policies and
procedures. Policies reflect the School Corporation's management statements of what should be done to
effect internal controls, and procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS
17
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper design or implementation of the components of a system of internal controls,
including policies and procedures that provide segregation of duties and additional oversight as needed,
the internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, the reports were not supported by the School Corporation's underlying
accounting records.
Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of
the federal award could result in the loss of future federal funding to the School Corporation.
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure all reports submitted on behalf of the
COVID-19 - Education Stabilization Fund program are supported by the School Corporation's underlying
accounting records.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.
FINDING 2023-002
Subject: COVID-19 - Education Stabilization Fund - Reporting
Federal Agency: Department of Education
Federal Program: COVID-19 - Education Stabilization Fund
Assistance Listings Number: 84.425D
Federal Award Number and Year (or Other Identifying Number): S425D210013
Pass-Through Entity: Indiana Department of Education
Compliance Requirement: Reporting
Audit Findings: Material Weakness, Other Matters
Condition and Context
The School Corporation had not properly designed or implemented a system of internal controls,
which would include appropriate segregation of duties, that would likely be effective in preventing, or
detecting and correcting, noncompliance.
The School Corporation was required to submit annual data reports to the Indiana Department of
Education via JotForm, a form/report builder. Data to be submitted included, but was not limited to, current
period expenditures, prior period expenditures, and expenditures per activity.
During the audit period the School Corporation submitted one ESSER I report, two ESSER II
reports, and two ESSER III reports, for a total of five reports. Although the Treasurer prepared the annual
data collection report, and the ESSER Program Director or Assistant Superintendent of Schools, both of
whom are knowledgeable about the program, reviewed and approved the report prior to submission, the
internal control was not effective and did not prevent, or detect and correct, errors prior to submission.
INDIANA STATE BOARD OF ACCOUNTS 16
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
All five reports were selected for testing. Neither of the ESSER II annual data reports were
accurately supported by the School Corporation's records. The errors identified were as follows:
The ESSER II, Year 1 report, which covered the period of July 1, 2020 to June 30, 2021,
reported total expenses of $58,917; however, the School Corporation's ledger for the same
period had total expenses of $1,306.
The ESSER II, Year 2 report, which covered the period of July 1, 2021 to June 30, 2022,
reported total expenses of $60,441; however, the School Corporation's ledger for the same
period had total expenses of $63,565.
The lack of effective internal controls and noncompliance were isolated to the S425D210013 grant
award.
Criteria
2 CFR 200.303 states in part:
"The non-Federal entity must:
(a) Establish and maintain effective internal control over the Federal award that provides
reasonable assurance that the non-Federal entity is managing the Federal award in
compliance with Federal statutes, regulations, and the terms and conditions of the Federal
award. These internal controls should be in compliance with guidance in 'Standards for
Internal Control in the Federal Government' issued by the Comptroller General of the
United States or the 'Internal Control Integrated Framework', issued by the Committee of
Sponsoring Organizations of the Treadway Commission (COSO). . . ."
2 CFR 200.302(b) states in part:
"The financial management system of each non-Federal entity must provide for the following
. . .
(2) Accurate, current, and complete disclosure of the financial results of each Federal
award or program in accordance with the reporting requirements set forth in §§ 200.328
and 200.329. . . ."
34 CFR 76.722 states: "A State may require a subgrantee to submit reports in a manner and format
that assists the State in complying with the requirements under 34 CFR 76.720 and in carrying out other
responsibilities under the program."
34 CFR 76.731 states: "A State and a subgrantee shall keep records to show its compliance with
program requirements."
Cause
A proper system of internal controls was not designed and implemented by management of the
School Corporation which would include segregation of key functions. Embedded within a properly
designed and implemented internal control system should be internal controls consisting of policies and
procedures. Policies reflect the School Corporation's management statements of what should be done to
effect internal controls, and procedures should consist of actions that would implement these policies.
INDIANA STATE BOARD OF ACCOUNTS
17
SOUTH GIBSON SCHOOL CORPORATION
SCHEDULE OF FINDINGS AND QUESTIONED COSTS
(Continued)
Effect
Without the proper design or implementation of the components of a system of internal controls,
including policies and procedures that provide segregation of duties and additional oversight as needed,
the internal control system cannot be capable of effectively preventing, or detecting and correcting, material
noncompliance. As a result, the reports were not supported by the School Corporation's underlying
accounting records.
Noncompliance with the provisions of federal statutes, regulations, and the terms and conditions of
the federal award could result in the loss of future federal funding to the School Corporation.
Questioned Costs
There were no questioned costs identified.
Recommendation
We recommended that management of the School Corporation establish a proper system of
internal controls and develop policies and procedures to ensure all reports submitted on behalf of the
COVID-19 - Education Stabilization Fund program are supported by the School Corporation's underlying
accounting records.
Views of Responsible Officials
For the views of responsible officials, refer to the Corrective Action Plan that is part of this report.