Audit 293407

FY End
2023-06-30
Total Expended
$9.43M
Findings
0
Programs
1
Year: 2023 Accepted: 2024-03-04
Auditor: Kcoe Isom LLP

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
20.106 Airport Improvement Program $8.02M Yes 0

Contacts

Name Title Type
VGLHH8NPF8W1 Chayleen Person Auditee
4067273404 Megan Connors Auditor
No contacts on file

Notes to SEFA

Accounting Policies: The  accompanying  Schedule  of  Expenditure  of  Federal  Awards  presents  the  activity  of  all  federal financial assistance of Great Falls International Airport Authority, Great Falls, Montana. The Airport Authority’s reporting entity is defined in note 1 to the Airport Authority’s financial statements. Federal financial assistance received directly from federal agencies is included in the schedule. No federal financial assistance received was passed through other government agencies. The accompanying Schedule of Expenditure of Federal Awards is presented using the modified accrual basis of accounting. Projects where expenditures and timing could not be appropriately determined or estimated will be recorded when they can be reasonably estimated or are known. The information in this schedule is presented in accordance with the requirements of Uniform Guidance. Therefore, some of the amounts presented in this schedule may differ from amounts presented or used in the preparation of the general purpose financial statements. The accompanying Schedule of Expenditure of Federal Awards is presented using the cost principles from Title 2 U.S. Code of Federal Regulations Part 200, Uniform Guidance Administrative Requirements, Subpart E Cost Principles. De Minimis Rate Used: N Rate Explanation: The Airport Authority did not elect to use the 10% de minimus indirect cost rate from Title 2 U.S. Code of Federal Regulations Part 200, Uniform Guidance Administrative Requirements, Subpart E Cost Principles.