Audit 292413

FY End
2023-06-30
Total Expended
$17.24M
Findings
0
Programs
1
Year: 2023 Accepted: 2024-02-27
Auditor: Eide Bailly LLP

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
10.766 Community Facilities Loans and Grants $17.24M Yes 0

Contacts

Name Title Type
CCDSA5ZCN9W4 Tammy Larson Auditee
7019682560 Brad Dejong Auditor
No contacts on file

Notes to SEFA

Title: Note 1 - Basis of Presentation Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. When applicable, such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. No federal financial assistance has been provided to a subrecipient. De Minimis Rate Used: N Rate Explanation: The Authority does not draw for indirect administrative expenses and has not elected to use the 10% de minimis cost rate. The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activity of Towner County Hospital Authority (Authority) under programs of the federal government for the year ended June 30, 2023. The information is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of the Authority, it is not intended to and does not present the financial position, changes in net assets, or cash flows of the Authority.
Title: Note 2 - Summary of Significant Accounting Policies Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. When applicable, such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. No federal financial assistance has been provided to a subrecipient. De Minimis Rate Used: N Rate Explanation: The Authority does not draw for indirect administrative expenses and has not elected to use the 10% de minimis cost rate. Expenditures reported on the Schedule are reported on the accrual basis of accounting. When applicable, such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. No federal financial assistance has been provided to a subrecipient.
Title: Note 3 - Indirect Cost Rate Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. When applicable, such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. No federal financial assistance has been provided to a subrecipient. De Minimis Rate Used: N Rate Explanation: The Authority does not draw for indirect administrative expenses and has not elected to use the 10% de minimis cost rate. The Authority does not draw for indirect administrative expenses and has not elected to use the 10% de minimis cost rate.
Title: Note 4 - Loan Programs Accounting Policies: Expenditures reported on the Schedule are reported on the accrual basis of accounting. When applicable, such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. No federal financial assistance has been provided to a subrecipient. De Minimis Rate Used: N Rate Explanation: The Authority does not draw for indirect administrative expenses and has not elected to use the 10% de minimis cost rate. At the beginning of the year, the Authority had an outstanding loan balance of $1,158,801 which was paid off during the year ended June 30, 2023. As such, this loan is not included in the Schedule. Expenditures reported in this Schedule consist of the advances made during the year on the construction loan of $12,760,648 plus expenditures incurred through June 30, 2023 with advances made subsequent to year end of $7,370,078 reduced by the amount of the interest reserve account of $2,887,951 for total expenditures included on the Schedule of $17,242,775. The outstanding loan balance as of June 30, 2023 was $12,760,648.