Audit 290863

FY End
2023-06-30
Total Expended
$1.33M
Findings
0
Programs
8
Year: 2023 Accepted: 2024-02-16

Organization Exclusion Status:

Checking exclusion status...

Findings

No findings recorded

Programs

ALN Program Spent Major Findings
84.425 Education Stabilization Fund $1.11M Yes 0
84.358 Rural Education $46,745 - 0
93.575 Child Care and Development Block Grant $43,481 - 0
84.048 Career and Technical Education -- Basic Grants to States $19,026 - 0
10.555 National School Lunch Program $14,846 - 0
10.553 School Breakfast Program $10,912 - 0
10.582 Fresh Fruit and Vegetable Program $7,875 - 0
10.649 Pandemic Ebt Administrative Costs $1,281 - 0

Contacts

Name Title Type
LA38FGSBRSM1 Andi Weisshaar Auditee
9704743365 Scott Szabo Auditor
No contacts on file

Notes to SEFA

Title: Note A – Basis of Presentation Accounting Policies: Expenditures reported on the Schedule are reported on the modified accrual basis of accounting. Therefore, some amounts presented in this Schedule may differ from amounts presented in, or used in the preparation of, the financial statement(s) of the federal program. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: Julesburg School District No. RE-1 did not pass through any federal grants to subrecipients. The accompanying schedule of expenditures of federal awards (the Schedule) includes the federal award activity of Julesburg School District No. RE-1 under programs of the federal government for the year ended June 30, 2023. The information in this Schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations (CFR), Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Because the Schedule presents only a selected portion of the operations of Julesburg School District No. RE-1, it is not intended to and does not present the financial position, changes in net position, or cash flows of Julesburg School District No. RE-1.
Title: Note B – Summary of Significant Accounting Policies Accounting Policies: Expenditures reported on the Schedule are reported on the modified accrual basis of accounting. Therefore, some amounts presented in this Schedule may differ from amounts presented in, or used in the preparation of, the financial statement(s) of the federal program. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: Julesburg School District No. RE-1 did not pass through any federal grants to subrecipients. Expenditures reported on the Schedule are reported on the modified accrual basis of accounting. Therefore, some amounts presented in this Schedule may differ from amounts presented in, or used in the preparation of, the financial statement(s) of the federal program. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement.
Title: Note C – Indirect Cost Rate Accounting Policies: Expenditures reported on the Schedule are reported on the modified accrual basis of accounting. Therefore, some amounts presented in this Schedule may differ from amounts presented in, or used in the preparation of, the financial statement(s) of the federal program. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: Julesburg School District No. RE-1 did not pass through any federal grants to subrecipients. Julesburg School District No. RE-1 has elected not to use the 10% de minimis indirect cost rate allowed under the Uniform Guidance.
Title: Note D – Subrecipients Accounting Policies: Expenditures reported on the Schedule are reported on the modified accrual basis of accounting. Therefore, some amounts presented in this Schedule may differ from amounts presented in, or used in the preparation of, the financial statement(s) of the federal program. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: Julesburg School District No. RE-1 did not pass through any federal grants to subrecipients. Julesburg School District No. RE-1 did not pass through any federal grants to subrecipients.
Title: Note E – Nonmonetary assistance Accounting Policies: Expenditures reported on the Schedule are reported on the modified accrual basis of accounting. Therefore, some amounts presented in this Schedule may differ from amounts presented in, or used in the preparation of, the financial statement(s) of the federal program. Such expenditures are recognized following the cost principles contained in the Uniform Guidance, wherein certain types of expenditures are not allowable or are limited as to reimbursement. De Minimis Rate Used: N Rate Explanation: Julesburg School District No. RE-1 did not pass through any federal grants to subrecipients. See the Notes to the SEFA for chart/table.