Audit 25743

FY End
2022-12-31
Total Expended
$17.91M
Findings
2
Programs
4
Year: 2022 Accepted: 2023-09-19

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
31186 2022-001 Material Weakness - E
607628 2022-001 Material Weakness - E

Programs

ALN Program Spent Major Findings
14.871 Section 8 Housing Choice Vouchers $9.37M - 0
14.850 Public and Indian Housing $6.38M Yes 1
14.872 Public Housing Capital Fund $1.98M - 0
14.182 Section 8 New Construction and Substantial Rehabilitation $179,999 - 0

Contacts

Name Title Type
TL8LQLN44E97 Brian Griswell Auditee
8649840579 Sergio Gonzalez Auditor
No contacts on file

Notes to SEFA

Accounting Policies: This schedule includes the federal grant activity of the South Carolina Regional Housing Authority No. 1 and is presentedon the full accrual basis of accounting. The information in this schedule is presented in accordance with the requirementsof the Uniform Guidance (Title 2 U.S. Code of Federal Regulations (CFR), Part 200, Uniform AdministrativeRequirements, Cost Principles, and Audit Requirements for Federal Awards). Therefore, some amounts presented in thisschedule may differ from amounts presented in, or used in the preparation of the basic financial statements. The Authorityhas not elected to use the 10% deminimis cost rate. De Minimis Rate Used: N Rate Explanation: The auditee did not use the de minimis cost rate.

Finding Details

2022-001 Eligibility: Public Housing Tenant Files Public and Indian Housing Program ? CFDA Number 14.850 Material Weakness in Internal Control, Material Noncompliance Condition: Out of a total tenant population of 1,275, 25 files were selected for testing. Exceptions were noted as follows: ? 6 files where the annual re-examination was not performed within 12 months. Criteria: 24 CFR 960.257 requires the Authority to conduct a re-examination of family income and composition at least annually and must make appropriate adjustments in the rent after consultation with the family and upon verification of the information. Questioned Costs: None. Effect: The Authority is not in compliance with all of the HUD requirements regarding eligibility and tenant re-examinations, which could result in incorrect total tenant payments for rent. Cause: During the year, the Authority changed when it would perform annual re-examinations to be the anniversary of the month the tenant was first admitted to the program. In implementing this change, the Authority failed to timely recognize that this would result in some tenants not having a re-examination within twelve months. Auditor?s Recommendation: The above-mentioned change will only result in non-timely annual re-examinations for some tenants for one time, and will effectively correct itself in future years. Nonetheless, the Authority should review all annual re-examinations for all tenants and immediately perform annual re-examinations for any remaining tenants that have not already had their next re-examination. Views of Responsible Officials of the Auditee: The Authority agrees with the finding and has taken corrective action. See the ?Action Taken? on the Corrective Action Plan.
2022-001 Eligibility: Public Housing Tenant Files Public and Indian Housing Program ? CFDA Number 14.850 Material Weakness in Internal Control, Material Noncompliance Condition: Out of a total tenant population of 1,275, 25 files were selected for testing. Exceptions were noted as follows: ? 6 files where the annual re-examination was not performed within 12 months. Criteria: 24 CFR 960.257 requires the Authority to conduct a re-examination of family income and composition at least annually and must make appropriate adjustments in the rent after consultation with the family and upon verification of the information. Questioned Costs: None. Effect: The Authority is not in compliance with all of the HUD requirements regarding eligibility and tenant re-examinations, which could result in incorrect total tenant payments for rent. Cause: During the year, the Authority changed when it would perform annual re-examinations to be the anniversary of the month the tenant was first admitted to the program. In implementing this change, the Authority failed to timely recognize that this would result in some tenants not having a re-examination within twelve months. Auditor?s Recommendation: The above-mentioned change will only result in non-timely annual re-examinations for some tenants for one time, and will effectively correct itself in future years. Nonetheless, the Authority should review all annual re-examinations for all tenants and immediately perform annual re-examinations for any remaining tenants that have not already had their next re-examination. Views of Responsible Officials of the Auditee: The Authority agrees with the finding and has taken corrective action. See the ?Action Taken? on the Corrective Action Plan.