FY End
2022-06-30
Total Expended
$6.27M
Findings
2
Programs
1
Year: 2022 Accepted: 2022-10-11
Auditor: Sobel & CO LLC

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
22820 2022-001 - - N
599262 2022-001 - - N

Programs

ALN Program Spent Major Findings
14.157 Supportive Housing for the Elderly $456,036 Yes 0

Contacts

Name Title Type
GCFAKLBSX1L3 John Westervelt Auditee
9735963984 Tara Del Gavio Auditor
No contacts on file

Notes to SEFA

Title: Loan/loan guarantee outstanding balances Accounting Policies: The accompanying schedule of expenditures of federal awards includes the federal grant activity of HUD Project No. 031 EE049 of Holy Rosary Senior Residence, Inc. (Project), and is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements. De Minimis Rate Used: N Rate Explanation: The auditee did not use the de minimis cost rate. SUPPORTIVE HOUSING FOR THE ELDERLY (14.157) - Balances outstanding at the end of the audit period were 5813700.
Title: Subrecipients: Accounting Policies: The accompanying schedule of expenditures of federal awards includes the federal grant activity of HUD Project No. 031 EE049 of Holy Rosary Senior Residence, Inc. (Project), and is presented on the accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Therefore, some amounts presented in this schedule may differ from amounts presented in, or used in the preparation of, the financial statements. De Minimis Rate Used: N Rate Explanation: The auditee did not use the de minimis cost rate. During the year ended June 30, 2022, the Project did not provide any funds relating to its federal program to subrecipients.

Finding Details

See Schedule of Findings and Questioned Costs for chart/table.
See Schedule of Findings and Questioned Costs for chart/table.