Audit 12386

FY End
2023-06-30
Total Expended
$868,194
Findings
6
Programs
11
Year: 2023 Accepted: 2024-01-19

Organization Exclusion Status:

Checking exclusion status...

Findings

ID Ref Severity Repeat Requirement
9056 2023-002 Material Weakness - N
9057 2023-002 Material Weakness - N
9058 2023-002 Material Weakness - N
585498 2023-002 Material Weakness - N
585499 2023-002 Material Weakness - N
585500 2023-002 Material Weakness - N

Programs

Contacts

Name Title Type
GCU9KEEXJLG6 Larry Worcester Auditee
2074558301 Gisele L. MacDonald Auditor
No contacts on file

Notes to SEFA

Accounting Policies: The accompanying Schedule of Expenditures of Federal Awards includes the federal grant activity of the Maine School Administrative District No. 45 and is presented on the modified accrual basis of accounting. The information in this schedule is presented in accordance with the requirements of Title 2 U.S. Code of Federal Regulations Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (Uniform Guidance). Therefore, some amounts presented in the schedule may differ from amounts presented in, or used in the preparation, of the basic financial statements. De Minimis Rate Used: N Rate Explanation: The auditee did not use the de minimus cost rate.

Finding Details

During the period under audit, the District spent $22,500 to upgrade field lighting, $47,500 for pavement and $5,277 on flooring using ESSER III funds. The Contractor was not notified of the prevailing wage requirement on these projects that were funded by these federal awards.
During the period under audit, the District spent $22,500 to upgrade field lighting, $47,500 for pavement and $5,277 on flooring using ESSER III funds. The Contractor was not notified of the prevailing wage requirement on these projects that were funded by these federal awards.
During the period under audit, the District spent $22,500 to upgrade field lighting, $47,500 for pavement and $5,277 on flooring using ESSER III funds. The Contractor was not notified of the prevailing wage requirement on these projects that were funded by these federal awards.
During the period under audit, the District spent $22,500 to upgrade field lighting, $47,500 for pavement and $5,277 on flooring using ESSER III funds. The Contractor was not notified of the prevailing wage requirement on these projects that were funded by these federal awards.
During the period under audit, the District spent $22,500 to upgrade field lighting, $47,500 for pavement and $5,277 on flooring using ESSER III funds. The Contractor was not notified of the prevailing wage requirement on these projects that were funded by these federal awards.
During the period under audit, the District spent $22,500 to upgrade field lighting, $47,500 for pavement and $5,277 on flooring using ESSER III funds. The Contractor was not notified of the prevailing wage requirement on these projects that were funded by these federal awards.